Cambridge Station Unit 2 Combustion Turbine Fuel Conversion Project

Project Details

Docket Numbers
Project Name
Cambridge Station Unit 2 Combustion Turbine Fuel Conversion Project
Applicant
Great River Energy
Location
Description

The project would replace existing natural gas burners with dual-fuel burners and install associated facilities to allow ULSD fuel oil combustion during periods of natural gas curtailment. The project is expected to protect GRE customers from extremely high energy prices.

Status
active

Project Contact

Contact
Andrew Levi
Phone

Project Summary

On March 11, 2022, GRE filed an application with the Commission for approval of a minor alteration to the site permit for the Unit 2 Combustion Turbine (Unit 2 CT). If approved, GRE would replace Unit 2 CT’s existing natural gas burners with dual-fuel burners to allow ULSD combustion in addition to natural gas combustion. The applicant indicates that ULSD as a back-up fuel source is necessary to provide power during natural gas curtailments. GRE defines “curtailment” to mean when natural gas is unavailable or ULSD is more economical than natural gas. The project has an anticipated operating life of 30 years.

New burners would replace existing burners on Unit 2 CT. The project would also require a 500,000-gallon ULSD AST, a 430,000-gallon demineralized water AST, and associated piping, pumps, and controls. A building extension to the south end of the existing pumphouse would be necessary to house some of this associated equipment. GRE will contract for a mobile reverse osmosis (RO) system that will use facility well water to make demineralized water. Demineralized water reduces NOX emissions when co-injected with ULSD into the new burners. Demineralized water will evaporate in the combustion process.

Key Project Documents

Date Title Description
April 12, 2023 Environmental Assessment Worksheet The EAW prepared for the Cambridge Station Fuel Conversion Project.

Docket Documents

View All Project Documents 

Date Title On Behalf Of Description
December 6, 2024 202412-212771-01 GREAT RIVER ENERGY Cambridge Facility - Stormwater Management
February 28, 2024 20242-203901-02 PUC FEBRUARY 1, 2024 MINUTES
February 23, 2024 20242-203772-01 PUC ORDER DENYING PETITION FOR RECONSIDERATION
January 24, 2024 20241-202582-01 PUC FEBRUARY 1, 2024 AGENDA
January 24, 2024 20241-202627-03 PUC NOVEMBER 9, 2023 MINTUES
January 19, 2024 20241-202346-02 PUC FEBRURY 1, 2024 AGENDA MEETING
January 5, 2024 20241-201884-01 GREAT RIVER ENERGY GRE RECONSIDERATION RESPONSE
December 27, 2023 202312-201592-01 CURE, MCEA, SIERRA CLUB NORTH STAR CHAPTER PETITION FOR RECONSIDERATION AND REHEARING
December 27, 2023 202312-201592-02 CURE, MCEA, SIERRA CLUB NORTH STAR CHAPTER APPENDIX_ PETITION FOR RECONSIDERATION
December 8, 2023 202312-201070-01 PUC DECISION ON NEED FOR EIS
December 7, 2023 202312-201052-01 PUC ORDER APPROVING MINOR ALTERATION APPLICATION
November 6, 2023 202311-200264-01 PUC NOVEMBER 9, 2023 AGENDA REVISED PAGE 9 TO BRIEFING PAPERS
November 1, 2023 202311-200109-01 PUC NOVEMBER 9, 2023 AGENDA
October 27, 2023 202310-199925-05 PUC NOVEMBER 9, 2023 AGENDA
October 2, 2023 202310-199320-01 LIUNA MINNESOTA/NORTH DAKOTA
October 2, 2023 202310-199325-01 GREAT RIVER ENERGY
October 2, 2023 202310-199307-01 IUOE LOCAL 49 AND NCSRC OF CARPENTERS
September 22, 2023 20239-199109-01 LIUNA MINNESOTA/NORTH DAKOTA
September 22, 2023 20239-199087-01 DOC EERA
August 25, 2023 20238-198523-01 PUC
August 25, 2023 20238-198517-01 DOC EERA
August 17, 2023 20238-198338-02 CURE APPENDIX A
August 17, 2023 20238-198318-01 GREAT RIVER ENERGY
August 17, 2023 20238-198338-01 CURE
July 24, 2023 20237-197709-01 PUC PAULA MARTI
July 18, 2023 20237-197574-01 PUC NOTICE OF EAW AVAILABILITY AND EAW MINOR ALTERATION COMMENT
July 17, 2023 20237-197549-01 EAST CENTRAL ENERGY LETTER OF SUPPORT
July 13, 2023 20237-197551-01 LAKE COUNTRY POWER LETTER OF SUPPORT
July 11, 2023 20237-197372-01 PUC REVISED EAW
July 7, 2023 20237-197305-01 PUC SUE HALLIGAN