Duluth Loop Reliability Project

Project Details

Docket Numbers
Project Name
Duluth Loop Reliability Project
Applicant
Minnesota Power
Location
St. Louis County
Description

On October 21, 2021, Minnesota Power (Applicant) submitted a Certificate of Need (CN) Application and a high voltage transmission line (HVTL) Route Permit Application (RPA) to the Minnesota Public Utilities Commission (Commission). The RPA is submitted under the alternative review process (Minnesota Statute 216E.04; Minnesota Rule 7850.2800-3900).

Status
active

Project Contact

Contact
Bill Storm
Phone

Project Summary

The Duluth Loop Project includes: (1) construction of about 14 miles of new 115 kV transmission line between the Ridgeview, Haines Road, and Hilltop Substations; (2) construction of a new approximately one-mile extension connecting an existing 230 kV transmission line to the Arrowhead Substation; (3) upgrades to the Ridgeview, Hilltop, Haines Road, and Arrowhead substations; and (4) reconfiguration, rebuild, and upgrade to existing transmission lines and communications infrastructure in the Project area.  Minnesota Power will own all of the facilities proposed for the Duluth Loop Project.

EA Scoping Survey

Interactive Map

Key Project Documents

Date Title Description
July 14, 2023 Draft EA Scoping Document Scoping focusses the Environmental Assessment on the most relevant information. It provides an opportunity for public input on the table of contents.
July 12, 2022 Environmental Assessment - Duluth Loop Reliability Project This environmental assessment has been prepared for the Duluth Loop Reliability Project, which includes construction of new 115 kilovolt (kV) transmission lines, extension of an existing 230kV transmission line, and upgrades to several substations. This EA evaluates the potential human and environmental impacts of the proposed project and possible mitigation measures including project alternatives. This EA is not a decision-making document, but rather serves as a guide for decision makers. The EA is intended to facilitate informed decisions by state agencies.
May 23, 2022 EA Scoping Decision Signed decision on the scope of the environmental assessment (EA) prepared for the Byron Solar Project and associated 345 kV transmission line. In addition to the applicant's proposed site and route, the EA will evaluate one additional route alternative for the proposed 345 kV transmission line.

The Department anticipates the EA will be available for review in late September 2022.
February 10, 2022 EA Scoping Comments Commission staff and Department held a Public Information EA Scoping Meeting on Wednesday, January 26, 2022, 6:00 p.m. at the AAD Shrine Meeting & Event Center 5152 Miller Trunk Hwy, Hermantown, MN 55811. The following comments were received.
January 27, 2022 Public Information & EA Scoping Meeting Presentation The state of Minnesota requires that potential human and environmental impacts be studied before the commission decides whether to grant a certificate of need and site permit. This is called environmental review. The intent of environmental review is informed decision making.
January 11, 2022 NOTICE OF PUBLIC INFORMATION AND ENVIRONMENTAL REVIEW SCOPING MEETING - Duluth Loop Reliability Project PLEASE TAKE NOTICE that the Minnesota Public Utilities Commission will hold in person and remote access public meetings on the application of Minnesota Power for a Certificate of Need and a High-Voltage Transmission Line Route Permit for their proposed
Duluth Loop Reliability Project. The purpose of the meetings is to provide information about the proposed project, the application review process being used, and to obtain public input on the environmental assessment that will be prepared by the Minnesota Department of
Commerce on this project.
October 25, 2021 Minnesota Power Duluth Loop Reliability Project - HVTL Route Permit Application Minnesota Power submits this application to the Minnesota Public Utilities Commission for a Certificate of Need and Route Permit to construct the Duluth Loop Reliability Project. The Duluth Loop Project includes: (1) construction of about 14 miles of new 115 kV transmission line between the Ridgeview, Haines Road, and Hilltop Substations; (2) construction of a new approximately one-mile extension connecting an existing 230 kV transmission line to the Arrowhead Substation; (3) upgrades to the Ridgeview, Hilltop, Haines Road, and Arrowhead substations; and (4) reconfiguration, rebuild, and upgrade to existing transmission lines and communications infrastructure in the Project area.

Docket Documents

View All Project Documents 

Date Title On Behalf Of Description
August 11, 2025 20258-221960-01 Minnesota Power July 2025 Complaint Report and Status Report
July 17, 2025 20257-221089-01 Minnesota Power June 2025 Complaint Report and Status Report
June 9, 2025 20256-219726-01 Minnesota Power Route Permit Compliance Filing Report and Complaint Report for June 2025
May 7, 2025 20255-218692-01 Minnesota Power Filing Report and Complaint Report for May 2025 Duluth Loop Reliability Project
April 11, 2025 20254-217558-01 Minnesota Power Duluth Loop - April 2025 Compliance Filing
March 12, 2025 20253-216322-01 Minnesota Power 2025 03 12 Duluth Loop - March Compliance Filing
February 10, 2025 20252-215153-01 Minnesota Power Duluth Loop - February 2025 Filing
January 10, 2025 20251-213810-01 Minnesota Power January 2025 Duluth Loop Status Report
January 9, 2025 20251-213718-01 PUC Letter to Minnesota Power
December 12, 2024 202412-212964-01 Minnesota Power 2024 12 12 Duluth Loop - December 2024 Compliance Filing
November 27, 2024 202411-212489-01 DOC EERA Transmission Line Plan and Profile
November 26, 2024 202411-212464-01 Minnesota Power Amended Maps to Nov 11 Filing
November 13, 2024 202411-211903-01 MINNESOTA POWER 2024 11 13 DULUTH LOOP_COMPLIANCE FILING NOVEMBER 2024
November 11, 2024 202411-211792-01 MINNESOTA POWER FILING LETTER - TRANSMISSION LINE PLAN AND PROFILE FILING
November 11, 2024 202411-211792-04 MINNESOTA POWER ATTACHMENT B - PART 2 OF 2
November 11, 2024 202411-211792-02 MINNESOTA POWER ATTACHMENT A - PROOF OF VMP AND FIELD REP MAILNG 101524
November 11, 2024 202411-211792-03 MINNESOTA POWER ATTACHMENT B - PART 1 OF 2
October 14, 2024 202410-210931-01 MINNESOTA POWER ROUTE PERMIT SECTIONS 6.2 AND 6.5 CONSTRUCTION PROGRESS
October 8, 2024 202410-210820-01 MINNESOTA POWER SEPTEMBER 2024 COMPLAINT REPORT
September 10, 2024 20249-210092-01 MINNESOTA POWER STATUS REPORT
August 9, 2024 20248-209383-01 MINNESOTA POWER AUGUST 2024 COMPLAINT REPORT
June 3, 2024 20246-207330-01 PUC TO MINNESOTA POWER
May 31, 2024 20245-207268-01 DOC EERA HILLTOP SUBSTATION
May 23, 2024 20245-207065-01 MINNESOTA POWER PLAN AND PROFILE FILING - HILLTOP SUBSTATION
May 8, 2024 20245-206518-01 MINNESOTA POWER VEGETATION MANAGEMENT PLAN
April 30, 2024 20244-206211-01 MINNESOTA POWER ROUTE PERMIT DISTRIBUTION
May 1, 2023 20235-195452-01 PUC EQB MONITOR
April 5, 2023 20234-194553-02 PUC FEBRUARY 16, 2023 AGENDA
April 3, 2023 20234-194456-05 PUC MAPS - PT 2 OF 2
April 3, 2023 20234-194456-01 PUC GRANTING CERTIFICATE OF NEED AND ISSUING ROUTE PERMIT - ORDER AND ROUTE PERMIT