Big Bend Wind Project
Project Details
Big Bend Wind, LLC, a subsidiary of Apex Clean Energy, Inc., is proposing the Big Bend Wind Project located within portions of Cottonwood and Watonwan counties, Minnesota. The Big Bend Wind Project is proposing to constructed and operate 47 Nordex N-163 (5.7 MW), 48 Vestas V162 (5.6 MW), or 49 GE-158 (5.5 MW) turbines, which will have a total generation capability of up to 308 megawatts (MWs). \r\n\r\n
Project Contact
Project Summary
Big Bend Wind, LLC, a subsidiary of Apex Clean Energy, Inc., is proposing the Big Bend Wind Project located within portions of Cottonwood and Watonwan counties, Minnesota. The Big Bend Wind Project is proposing to constructed and operate 47 Nordex N-163 (5.7 MW), 48 Vestas V162 (5.6 MW), or 49 GE-158 (5.5 MW) turbines, which will have a total generation capability of up to 308 megawatts (MWs).
The Big Bend Wind Project is being proposed as a potential hybrid wind energy and solar energy generation project, and could be constructed and operated in coordination with the Red Rock Solar Project. Red Rock Solar, LLC, a subsidiary of Apex Clean Energy, Inc., is pursuing a separate site permit for the Red Rock Solar Project, under Docket #GS-19-620. The Red Rock Solar Project is proposed to generate up to 60 MWs, and if approved, constructed and operated the total solar energy generation would reduce the total wind energy generation at the Big Bend Wind Project, so the total energy generation at the two facilities would not exceed 314 MWs.
The Big Bend Wind Project will require an approximately 18 mile long, 161 kilovolt (kV) transmission line to be constructed and operate to transmit generated wind energy to the electrical grid interconnection. The proposed 161 kV transmission line could also provide solar energy transmission for the proposed Red Rock Solar Project. Big Bend Wind, LLC has submitted an application for a route permit for the proposed transmission line under Docket #TL-19-621.
Key Project Documents
Date | Title | Description |
---|---|---|
01/25/2022 | Errata to the Environmental Assessment (with corrected Chapter 8 Table formatting) | Corrections to the EA completed for the Big Bend Wind, Red Rock Solar, and Big Bend HVLT Projects. |
09/28/2022 | LWECS Site Permit Issued 9-28-22 | Site Permit issued by the Commission for the Big Bend Wind Project. |
10/13/2021 | Revised Site Layout Summary | Big Bend Wind, LLC provided a summary of the revisions and amendments to the proposed Big Bend Wind Project. |
04/09/2021 | Public Information and Environmental Scoping - Presentations | Commission staff, Applicant, and DOC-EERA staff presentations from the April 1, 2021 virtual Public Information and Environmental Scoping Meeting. |
01/11/2021 | DOC-EERA - Reply Comments on Application Acceptance and Completeness | DOC-EERA submitted reply comments to the Public Utilities Commission regarding the Big Bend Wind Project Site Permit Application acceptance and completeness. |
09/14/2021 | Big Bend Wind Settlement Agreement | A Settlement Agreement has been reached between Big Bend Wind, LLC and the Intervening Parties to address the concerns of Intervening Parties that the construction and operation of the proposed Big Bend Wind Project will have visual impacts on the users of the Jeffers Petroglyphs site. |
01/11/2021 | DOC-EERA Comments and Recommendations on Application Acceptance and Completeness | DOC-EERA submitted comments and recommendations to the Public Utilities Commission regarding the Big Bend Wind Project Site Permit Application acceptance and completeness. |
01/18/2022 | Big Bend Wind and Red Rock Solar Environmental Assessment | Combined Environmental Report and Environmental Assessment for the Big Bend Wind, Red Rock Solar, and Big Bend HVTL Projects. |
09/20/2021 | Amended Site Permit Application | Big Bend Wind, LLC has filed an Amended Site Permit Application for the proposed changes to the Big Bend Wind Project. |
01/11/2021 | Big Bend Wind Project - Site Permit Application | Big Bend Wind, LLC submitted a Site Permit Application (SPA) for a Large Wind Energy Conversation System (LWECS) with the Minnesota Public Utilities Commission on November 9, 2020. |
Docket Documents
View Project Documents (last 30) View All Project Documents
Date | Document ID | On Behalf Of | Description |
---|---|---|---|
July 28, 2025 | 20257-221472-01 | Big Bend Wind, LLC | Big Bend Wind - Quarterly Update |
July 7, 2025 | 20257-220704-01 | DOC | |
July 7, 2025 | 20257-220704-02 | DOC | |
April 22, 2025 | 20254-218003-01 | Big Bend Wind, LLC | Quarterly Update |
January 28, 2025 | 20251-214489-01 | Big Bend Wind, LLC | Quarterly Update |
January 23, 2025 | 20251-214274-01 | Big Bend Wind, LLC | Revised Site Permit Distribution Filing |
January 15, 2025 | 20251-214036-01 | Big Bend Wind, LLC | Supplemental Filing -PPA |
December 23, 2024 | 202412-213281-01 | PUC | Revised Site Permit |
November 26, 2024 | 202411-212422-01 | PUC | November 26, 2024 Consent |
November 26, 2024 | 202411-212440-01 | PUC | |
November 21, 2024 | 202411-212268-01 | PUC | PROPOSED CONSENT ITEMS |
October 28, 2024 | 202410-211386-01 | BIG BEND WIND AND RED ROCK SOLAR | QUARTERLY UPDATE |
October 16, 2024 | 202410-211093-01 | LIUNA MINNESOTA/NORTH DAKOTA | |
October 16, 2024 | 202410-211037-01 | DOC EERA | SUPPLEMENTAL COMMENTS |
October 11, 2024 | 202410-210882-01 | BIG BEND WIND, LLC AND RED ROCK SOLAR, LLC | |
October 11, 2024 | 202410-210885-01 | BIG BEND WIND, LLC AND RED ROCK SOLAR, LLC | |
October 4, 2024 | 202410-210737-01 | IUOE LOCAL 49 AND NCSRC OF CARPENTERS | |
October 4, 2024 | 202410-210718-01 | DOC EERA | PPA AND CONSTRUCTION DEADLINE EXTENSION |
September 20, 2024 | 20249-210369-01 | PUC | ON SITE PERMIT EXTENSION REQUEST |
September 18, 2024 | 20249-210300-01 | BIG BEND WIND, LLC | FILING LETTER WITH REQUEST FOR EXTENSION |
July 26, 2024 | 20247-209010-01 | BIG BEND WIND, LLC AND RED ROCK SOLAR, LLC | QUARTERLY UPDATE |
April 26, 2024 | 20244-206006-02 | BIG BEND WIND, LLC AND RED ROCK SOLAR, LLC | 2024-04-26 BB AND RR QUARTERLY UPDATE |
January 26, 2024 | 20241-202713-01 | BIG BEND WIND, LLC AND RED ROCK SOLAR, LLC | QUARTERLY UPDATE |
October 27, 2023 | 202310-199933-02 | BIG BEND WIND, LLC AND RED ROCK SOLAR, LLC | BIG BEND WIND AND RED ROCK SOLAR QUARTERLY UPDATE |
July 28, 2023 | 20237-197849-01 | BIG BEND WIND, LLC AND RED ROCK SOLAR, LLC | 2023 QUARTERLY UPDATE |
April 17, 2023 | 20234-194840-02 | BIG BEND WIND, LLC AND RED ROCK SOLAR, LLC | BB AND RR QUARTERLY UPDATE |
January 30, 2023 | 20231-192729-02 | BIG BEND WIND AND RED ROCK SOLAR | BB AND RR QUARTERLY UPDATE |
November 15, 2022 | 202211-190664-03 | BIG BEND WIND, LLC AND RED ROCK SOLAR, LLC | BBRR FILING LETTER WITH EXHIBIT A 11.15.22 |
October 26, 2022 | 202210-190160-01 | BIG BEND/RED ROCK | QUARTERLY UPDATE COMPLIANCE FILING |
September 28, 2022 | 20229-189351-10 | PUC | ATTACHMENT 1 |