Three Waters Wind Farm

Project Details

Docket Numbers
Project Name
Three Waters Wind Farm
Applicant
Scout Clean Energy, LLC dba Three Waters Wind Farm, LLC
Location
Jackson County
Description

Three Waters Wind Farm, LLC is proposing the 201 MW Three Waters Wind Farm in Jackson County, Minnesota. The proposed project area also extends into Osceola and Dickinson Counties, Iowa. The proposed project is primarily planned to be located within Jackson County, Minnesota, but project areas within Osceola and/or Dickinson Counties, Iowa may be utilized as alternative locations should they be necessary. Three Waters Wind Farm, LLC has also applied for a Certificate of Need (CN), which can be found under docket #IP-7002/CN-19-154.

Status
active

Project Contact

Contact
Richard Davis
Phone

Key Project Documents

Date Title Description
07/14/2020 Applicant - Notice of Change of Ownership Three Waters Wind Farm, LLC previously owned by Scout Clean Energy was acquired by Twin Wind, LLC, a subsidiary of NextEra Energy Resources, LLC.
06/08/2020 EERA Letter Requesting an Application Amendment EERA requested the Applicant file a stand alone Application Amendment document with updated information for the proposed Three Waters Wind Farm. The proposed turbine locations had been revised from the initial application.
05/11/2020 EERA Comments and Recommendations - Preliminary Draft Site Permit EERA provided comments and recommendations to the Commission, along with a Preliminary Draft Site Permit (PDSP) for the proposed Three Waters Wind Farm.
07/17/2020 Applicant - Motion to Suspend Procedural Schedule The Applicant requested a suspension of the procedural schedule for the Three Waters Wind Farm, to allow the new project owner to evaluate project and schedule details.
03/10/2020 Public Information and ER Scoping Meeting Presentations Presentations given by Commission staff, the Applicant, and EERA staff at the Public Information and Scoping Meeting held on February 20, 2020 in Jackson, MN.
02/12/2020 Notice Three Waters Wind Farm - Public Meeting Canceled and Rescheduled The Three Waters Wind Project scheduled for Thursday, February 13, 2020 has been canceled, and is rescheduled for Thursday, February 20, 2020.
07/30/2020 Applicant - Project Schedule Update The Applicant provided a project update that indicates the procedural schedule would be placed on hold through 2020, allowing for further development of the proposed Three Waters Wind Farm. The procedural schedule would than resume and move forward in 2021.
03/10/2020 All Agency Comments Received by EERA All agency comments received by EERA during the January 23, 2020 to February 28, 2020 comment period on the Three Waters Wind Farm.
03/13/2020 Environmental Report Scoping Decision Department of Commerce developed and issued the Environmental Report Scoping Decision for the Three Waters Wind Farm.
01/23/2020 Notice of Public Information and Environmental Report Scoping Meeting Notice of Public Information and Environmental Report Scoping Meeting for the Three Waters Wind Farm to be held in Jackson, Minnesota on Thursday, February 13, 2020 at 6 pm. The associated public comment period ends on Friday, February 28, 2020.
06/22/2020 Public Utilities Commission - Order Issuing Draft Site Permit The Commission issued a Draft Site Permit (DSP) for the proposed Three Waters Wind Farm. The Order also detailed requirements of the Applicant to file a stand alone environmental review of proposed project amendments and review of these amendments by EERA.
08/18/2020 Office of Administrative Hearings - Third Continuance Order The honorable Administrative Law Judge (ALJ) Jim Mortenson has issued a third continuance order with regard to the Three Waters Wind Farm. The Order identifies a pre-hearing conference scheduled for September 30, 2020 to discuss a public hearing, and related events, schedule proposed by the ALJ, and other procedural options the Applicant has available at this time.
11/05/2019 DOC-EERA Comments and Recommendations DOC-EERA Comments and Recommendations on Application Acceptance of Three Waters Wind Site Permit Application.
03/10/2020 All Public Comments Received by EERA All public comments received by EERA during the January 23, 2020 to February 28, 2020 comment period for the Three Waters Wind Farm.
10/22/2019 Site Permit Application - Initial Filing and Revised Application Filings Site Permit Application for the proposed 201 MW Three Waters Wind Farm in Jackson County, Minnesota. Includes the Site Permit Application, Figures, and Appendices included in the initial filing, and includes all revised and corrected site permit application components.

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
November 13, 2020 202011-168298-02 PUC MINUTES JUNE 11, 2020
October 27, 2020 202010-167690-01 OAH DISMISSAL ORDER
October 20, 2020 202010-167508-01 PUC NOTICE AND ORDER APPROVING PETITION TO WITHDRAW FILINGS
September 24, 2020 20209-166818-02 OAH FOURTH CONTINUANCE ORDER
September 18, 2020 20209-166699-01 OVERLAND - LEGALECTRIC DETERMINATION
September 18, 2020 20209-166672-01 THREE WATERS WIND FARM, LLC MOTION TO WITHDRAW SITE PERMIT AND CERTIFICATE OF NEED APPLICATIONS
September 17, 2020 20209-166965-01 PUC
August 18, 2020 20208-165983-02 OAH THIRD CONTINUANCE ORDER
August 13, 2020 20208-166274-02 COURT REPORTER PREHEARING CONFERENCE - 8-13-20
August 7, 2020 20208-165667-01 OAH SCHEDULING ORDER
July 30, 2020 20207-165393-01 THREE WATERS WIND FARM, LLC PROJECT UPDATE
July 23, 2020 20207-165236-02 OAH SECOND CONTINUANCE ORDER
July 17, 2020 20207-165043-01 THREE WATERS WIND FARM, LLC MOTION TO SUSPEND PROCEDURAL SCHEDULE OF THREE WATERS WIND FARM, LLC
July 14, 2020 20207-164912-02 THREE WATERS WIND FARM, LLC NOTIFICATION OF CHANGE OF OWNERSHIP
July 14, 2020 20207-164917-02 THREE WATERS WIND FARM, LLC WITHDRAWAL OF COUNSEL
July 10, 2020 20207-164815-01 PUC NOTICE OF PUBLIC HEARING
July 10, 2020 20207-164828-03 PUC CERTIFICATE OF SERVICE AND SERVICE LISTS
July 10, 2020 20207-164815-03 PUC CERTIFICATE OF SERVICE AND SERVICE LISTS
July 10, 2020 20207-164828-01 PUC NOTICE OF PUBLIC HEARING
July 6, 2020 20207-164659-02 DOC-EERA CONFIRMATION OF SITE PERMIT APPLICATION AMENDMENT
July 6, 2020 20207-164667-02 OVERLAND-LEGALECTRIC COMPLETENESS REVIEW AND ORDER MISSING 7854.0600 AND APPLICATION INCOMPLETE
July 2, 2020 20207-164633-02 THREE WATERS WIND FARM, LLC SITE PERMIT AMENDMENT_PART2 OF 8
July 2, 2020 20207-164633-05 THREE WATERS WIND FARM, LLC SITE PERMIT AMENDMENT_PART5 OF 8
July 2, 2020 20207-164633-08 THREE WATERS WIND FARM, LLC SITE PERMIT AMENDMENT_PART8 OF 8
July 2, 2020 20207-164633-03 THREE WATERS WIND FARM, LLC SITE PERMIT AMENDMENT_PART3 OF 8
July 2, 2020 20207-164633-06 THREE WATERS WIND FARM, LLC SITE PERMIT AMENDMENT_PART6 OF 8
July 2, 2020 20207-164633-01 THREE WATERS WIND FARM, LLC SITE PERMIT AMENDMENT_PART1 OF 8
July 2, 2020 20207-164633-04 THREE WATERS WIND FARM, LLC SITE PERMIT AMENDMENT_PART4 OF 8
July 2, 2020 20207-164633-07 THREE WATERS WIND FARM, LLC SITE PERMIT AMENDMENT_PART7 OF 8
June 26, 2020 20206-164310-03 ASSOCIATION OF FREEBORN COUNTY LANDOWNERS SUMMONS AND COMPLAINT - STATE OF MINNESOTA EX REL ASSOCIATION OF FREEBORN COUNTY LANDOWNERS V MINNESOTA PUBLIC UTILITIES COMMISSION