Rochester Natural Gas Pipeline Project
Project Details
Minnesota Energy Resources Corporation is proposing to install approximately 13.1 miles of new natural gas pipeline west and south of the city of Rochester in Olmsted County, Minnesota
Project Contact
Project Summary
Minnesota Energy Resources Corporation (MERC) proposes to construct approximately 13.1 miles of new natural gas pipeline west and south of the city of Rochester in Olmsted County, Minnesota. The proposed pipeline will include installation of approximately 5.1 miles of 16-inch outside diameter and 8.0 miles of 12-inch outside diameter steel pipeline designed to operate at pressures between 400-475 pounds per square inch gauge (psig). The proposed project will tie together the northern and southern portions of MERC's existing natural gas distribution system.
The proposed project will also include construction of two town border stations. Town border stations receive high pressure natural gas from the natural gas transmission system (900-1,000 psig) and regulate it down for use on the local distribution system (400-500 psig). The project will also include construction of a district regulator station. District regulator stations take high pressure distribution natural gas (400-500 psig) and regulate it down further (60-100 psig) for delivery to the low pressure distribution system.
MERC is requesting a route permit for a 500-foot-wide route. The proposed project will require a 50-foot-wide permanent right-of-way, and an additional 50-foot-wide construction right-of-way.
The proposed project will be phased. Construction is anticipated to begin in 2017 and be completed in 2022. The project is anticipated to cost $44 million.
Key Project Documents
Date | Title | Description |
---|---|---|
May 5, 2017 | Route Permit for the Rochester Natural Gas Pipeline Project. | The Commission has issued a permit for the Rochester Natural Gas Pipeline Project |
September 16, 2016 | Comparative Environmental Analysis for the Rochester Natural Gas Pipeline Project | The Comparative Environmental Analysis is a written document developed and prepared by EERA that contains an overview of the resources and potential human and environmental impacts and mitigation measures associated with the proposed project |
November 9, 2015 | Supplement to the Route Permit Application | Minnesota Energy Resources Corporation has filed supplemental information to its route permit application to construct the Rochester Natural Gas Pipeline Project in Olmsted County, Minnesota |
November 3, 2015 | Route Permit Application for the Rochester Natural Gas Pipeline Project | Minnesota Energy Resources Corporation filed an application for a route permit with the Minnesota Public Utilities Commission to construct the Rochester Natural Gas Pipeline Project in Olmsted County, Minnesota |
Docket Documents
View Project Documents (last 30) View All Project Documents
Date | Title | On Behalf Of | Description |
---|---|---|---|
January 30, 2024 | 20241-202851-01 | MINNESOTA ENERGY RESOURCES CORPORATION | MERC PIPELINE COMPLETION CERTIFICATION |
September 15, 2022 | 20229-189113-01 | MINNESOTA ENERGY RESOURCES CORPORATION | AUGUST 2022 COMPLAINT REPORT |
September 15, 2022 | 20229-189113-02 | MINNESOTA ENERGY RESOURCES CORPORATION | AUGUST 2022 STATUS REPORT |
August 24, 2022 | 20228-188578-01 | MINNESOTA ENERGY RESOURCES CORPORATION | 20220824_MERC_RESTORATION STATION 90 |
August 15, 2022 | 20228-188333-01 | MINNESOTA ENERGY RESOURCES CORPORATION | JULY 2022 STATUS REPORT |
August 15, 2022 | 20228-188333-02 | MINNESOTA ENERGY RESOURCES CORPORATION | JULY 2022 ROCHESTER COMPLAINT REPORT |
July 15, 2022 | 20227-187487-01 | MINNESOTA ENERGY RESOURCES CORPORATION | JUNE 2022 ROUTE PERMIT STATUS REPORT |
July 15, 2022 | 20227-187487-02 | MINNESOTA ENERGY RESOURCES CORPORATION | JUNE 2022 COMPLAINT REPORT |
July 7, 2022 | 20227-187252-01 | MINNESOTA ENERGY RESOURCES CORPORATION | MERC_5.6.21_12INCHSEGMENT3_COMPLETE |
June 15, 2022 | 20226-186650-01 | MINNESOTA ENERGY RESOURCES CORPORATION | MAY 2022 COMPLAINT REPORT |
June 15, 2022 | 20226-186683-01 | MINNESOTA ENERGY RESOURCES CORPORATION | MAY 2022 ROUTE PERMIT STATUS REPORT |
May 13, 2022 | 20225-185793-01 | MINNESOTA ENERGY RESOURCES CORPORATION | APRIL 2022 ROUTE PERMIT COMPLAINT PROCEDURE |
May 13, 2022 | 20225-185767-01 | MINNESOTA ENERGY RESOURCES CORPORATION | APRIL 2022 ROUTE PERMIT STATUS REPORT |
April 14, 2022 | 20224-184772-01 | MINNESOTA ENERGY RESOURCES CORPORATION | ROCHESTER - MARCH 2022 COMPLAINT REPORT |
April 14, 2022 | 20224-184772-02 | MINNESOTA ENERGY RESOURCES CORPORATION | MARCH 2022 ROUTE PERMIT STATUS REPORT |
March 15, 2022 | 20223-183787-01 | MINNESOTA ENERGY RESOURCES CORPORATION | FEBRUARY 2022 MONTHLY STATUS REPORT |
March 15, 2022 | 20223-183800-01 | MINNESOTA ENERGY RESOURCES CORPORATION | FEBRUARY 2022 COMPLAINT REPORT |
February 15, 2022 | 20222-182798-01 | MINNESOTA ENERGY RESOURCES CORPORATION | JANUARY 2022 COMPLAINT REPORT |
February 15, 2022 | 20222-182801-01 | MINNESOTA ENERGY RESOURCES CORPORATION | JANUARY 2022 STATUS REPORT |
February 15, 2022 | 20222-182797-01 | MINNESOTA ENERGY RESOURCES CORPORATION | MERC DRS AS-BUILT GPS_2.15.2022 |
January 26, 2022 | 20221-182040-01 | MINNESOTA ENERGY RESOURCES CORPORATION | STATUS REPORT - WEEK OF JANUARY 15TH, 2022 |
January 19, 2022 | 20221-181724-01 | MINNESOTA ENERGY RESOURCES CORPORATION | STATUS REPORT - WEEK OF JANUARY 8TH, 2022 |
January 14, 2022 | 20221-181535-01 | MINNESOTA ENERGY RESOURCES CORPORATION | DECEMBER 2021 COMPLAINT REPORT |
January 12, 2022 | 20221-181447-01 | MINNESOTA ENERGY RESOURCES CORPORATION | STATUS REPORT - WEEK OF JANUARY 1ST, 2022 |
January 6, 2022 | 20221-181278-01 | MINNESOTA ENERGY RESOURCES CORPORATION | MERC 12INCH SEGMENT 3 AS-BUILT GPS |
January 5, 2022 | 20221-181248-01 | MINNESOTA ENERGY RESOURCES CORPORATION | STATUS REPORT - WEEK OF DECEMBER 25, 2021 |
December 29, 2021 | 202112-181060-01 | MINNESOTA ENERGY RESOURCES CORPORATION | STATUS REPORT - WEEK OF DECEMBER 18, 2021 |
December 22, 2021 | 202112-180942-01 | MINNESOTA ENERGY RESOURCES CORPORATION | STATUS REPORT - WEEK OF DECEMBER 11, 2021 |
December 15, 2021 | 202112-180739-02 | MINNESOTA ENERGY RESOURCES CORPORATION | NOVEMBER 2021 MONTHLY COMPLAINT REPORT |
December 15, 2021 | 202112-180739-01 | MINNESOTA ENERGY RESOURCES CORPORATION | DECEMBER 4 -10 2021 WEEKLY ROUTE PERMIT STATUS REPORT |