Description

Freeborn Wind Energy, LLC, an affiliate of Invenergy, LLC, has proposed to construct and operate the 200 MW Freeborn Wind Farm in Freeborn County, Minnesota and Worth County, Iowa

Status
active

Project Contact

Contact
Richard Davis
Phone

Project Summary

The Freeborn Wind Farm is proposed to generate up to 200 megawatts (MW) total, with 84 MW being generated in Minnesota and the remaining 116 MW being generated in Iowa. The Minnesota portion of the proposed project will consist of up to 42 - 2.0 MW wind turbines, Vestas brand models V116 and V110 are currently being considered for use. Associated project facilities will include gravel access roads, buried electrical collector lines, operation and maintenance facility, a project substation, and a permanent meteorological tower.  

A  transmission line will be constructed to connect the project substation to the electrical transmission grid; this transmission line will be reviewed and a decision will be issued under a separate route permit process (TL-17-322).

The Commission issued a site permit for the Freeborn Wind Farm on December 19, 2018.  The Commission authorized transfer of the site permit to Northern States Power Company (Xcel Energy) on October 22, 2019. The wind farm is anticipated to be operational in December 2020. 

Key Project Documents

Date Title Description
05/10/2019 Commission Order Amending Site Permit The Commission's order amending the site permit for the Freeborn Wind Farm. The amendments clarify several sections of the site permit.
12/11/2018 Commission Order Transferring Site Permit The Commission's order transferring the site permit for the Blazing Star Wind Farm to Northern States Power Company (Xcel Energy).
12/19/2018 Commission Order Issuing a Site Permit The Commission's order issuing a site permit for the Freeborn Wind Farm.
05/10/2019 Commission Order Amending Site Permit The Commission's order amending the site permit for the Freeborn Wind Farm. The amendments clarify several sections of the site permit.
07/12/2017 Freeborn Wind Farm Site Permit Application Large Wind Energy Conversion System (LWECS) Site Permit Application filed by Freeborn Wind Energy, LLC for the proposed Freeborn Wind Farm

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
September 12, 2025 20259-222932-02 Xcel Energy Consolidated Wind Complaints
September 12, 2025 20259-222932-01 Xcel Energy Consolidated Wind Complaints
August 13, 2025 20258-222024-01 Xcel Energy Consolidated Wind Complaint Cover Letter
August 13, 2025 20258-222024-02 Xcel Energy Consolidated Wind Complaint Report
July 15, 2025 20257-220968-01 Xcel Energy 2nd Quarterly Avian and Bat Incident Report
July 14, 2025 20257-220901-02 Xcel Energy Consolidated Wind Complaints
July 14, 2025 20257-220901-01 Xcel Energy Consolidated Wind Complaints
June 13, 2025 20256-219882-01 Xcel Energy Compliance Filing PUBLIC
June 13, 2025 20256-219882-02 Xcel Energy Complaint Report PUBLIC
May 14, 2025 20255-218940-02 Xcel Energy April 2025 Consolidated Wind Complaints
May 14, 2025 20255-218940-01 Xcel Energy Consolidated Wind Complaints
April 14, 2025 20254-217584-01 Xcel Energy Consolidated Monthly Complaint Report
April 14, 2025 20254-217584-02 Xcel Energy March 2025 Complaint Report
April 11, 2025 20254-217504-01 Xcel Energy Q1 ABPP Report
March 14, 2025 20253-216403-02 Xcel Energy February 2025 Complaint Report
March 14, 2025 20253-216393-01 Xcel Energy Annual Avian and Bat Protection Plan Report
March 14, 2025 20253-216403-01 Xcel Energy February 2025 Complaint Report
February 14, 2025 20252-215409-02 Xcel Energy January 2025 Complaint Report
February 14, 2025 20252-215409-01 Xcel Energy January 2025 Wind Complaint Cover Letter
January 31, 2025 20251-214757-02 Xcel Energy 2024 Annual Wind Report-Att A
January 31, 2025 20251-214757-01 Xcel Energy 2024 Annual Wind Report
January 15, 2025 20251-213952-02 Xcel Energy Consolidated December 2024 Complaint Report
January 15, 2025 20251-213952-01 Xcel Energy Consolidated December 2024 Complaint Report
January 14, 2025 20251-213935-01 Xcel Energy Q4 2024 ABPP Report
December 13, 2024 202412-212993-04 Xcel Energy Complaint Report PUBLIC
December 13, 2024 202412-212993-01 Xcel Energy Compliance Filing PUBLIC
November 15, 2024 202411-211972-14 XCEL ENERGY OCTOBER CONSOLIDATED WIND 2024 COMPLAINT REPORT
November 15, 2024 202411-211972-03 XCEL ENERGY OCTOBER CONSOLIDATED WIND 2024 COMPLAINT REPORT
October 15, 2024 202410-210971-12 XCEL ENERGY SEPTEMBER 2024 WIND COMPLAINTS
October 15, 2024 202410-210968-01 XCEL ENERGY AVIAN AND BAT INCIDENT QUARTERLY REPORT