Elm Creek II Wind Project

Project Details

Docket Numbers
Project Name
Elm Creek II Wind Project
Applicant
Heartland Wind, LLC,
Location
Jackson County, Martin County
Description

Heartland Wind, LLC, LWECS Site Permit Application for a 150 MW Wind Farm in Jackson and Martin Counties

Status
active

Project Contact

Contact
Richard Davis
Phone

Project Summary

Heartland Wind, LLC (Heartland Wind), a wholly-owned subsidiary of Iberdrola Renewables, Inc., has submitted an application to the Minnesota Public Utilities Commission for a site permit to construct and operate the Elm Creek II Wind Project (Project). The proposed Project is a Large Wind Energy Conversion System, as defined in the Wind Siting Act, Minnesota Statutes Chapter 216F. The Project is located in Jackson and Martin counties and will be up to 150 MW in nameplate capacity, consisting of up to 100 wind turbine generators.

Associated Project facilities include gravel access roads, a wind electrical collection system, an Operations and Maintenance building, permanent meteorological towers, and a Sonic Detection and Ranging (SODAR) unit. The Project is expected to come online as early as autumn 2010.

A separate application for a Certificate of Need has been filed with the Commission for this project.  To review relevant documents in that matter, search eDockets using year "9" and Number "471".

Key Project Documents

Date Title Description
July 24, 2025 Elm Creek Wind II Notice of Public Information Elm Creek Wind II Notice of Public Information

Docket Documents

View All Project Documents 

Date Title On Behalf Of Description
August 7, 2025 20258-221851-01 PUC
August 7, 2025 20258-221849-01 PUC Meeting Presentation
August 7, 2025 20258-221859-01 AVANGRID July 2025 Complaint Report
August 7, 2025 20258-221850-01 PUC
August 6, 2025 20258-222207-02 Shaddix & Associates - Stenographic Court Reporters Virtual Public Hearing on 8-6-25
August 5, 2025 20258-222207-01 Shaddix & Associates - Stenographic Court Reporters Public Hearing in Jackson on 8-5-25
July 18, 2025 20257-221133-01 PUC NOTICE OF PUBLIC INFORMATION MEETINGS
July 9, 2025 20257-220799-01 PUC Notice of Legislative Changes
July 2, 2025 20257-220601-01 AVANGRID June 2025 Complaint Extradordinary Letter
June 20, 2025 20256-220088-01 DOC-EERA Comments and Recommendations, Draft Site Permit
June 10, 2025 20256-219780-01 Avangrid Power, LLC
June 9, 2025 20256-219706-01 AVANGRID May 2025 Complaint Extradordinary Letter
May 12, 2025 20255-218786-01 Avangrid April 2025 Complaint Filing
April 25, 2025 20254-218140-01 AVANGRID March 2025 Complaint Report
March 31, 2025 20253-217028-31 Avangrid Power, LLC Elm Creek II Repower Application - Map 15
March 31, 2025 20253-217028-13 Avangrid Power, LLC Elm Creek II Repower Application - Appendix L
March 31, 2025 20253-217028-28 Avangrid Power, LLC Elm Creek II Repower Application - Map 12
March 31, 2025 20253-217028-21 Avangrid Power, LLC Elm Creek II Repower Application - Map 05
March 31, 2025 20253-217028-22 Avangrid Power, LLC Elm Creek II Repower Application - Map 06
March 31, 2025 20253-217028-36 Avangrid Power, LLC Elm Creek II Repower Application - Appendix B
March 31, 2025 20253-217028-17 Avangrid Power, LLC Elm Creek II Repower Application - Map 01
March 31, 2025 20253-217028-26 Avangrid Power, LLC Elm Creek II Repower Application - Map 10
March 31, 2025 20253-217028-20 Avangrid Power, LLC Elm Creek II Repower Application - Map 04
March 31, 2025 20253-217028-29 Avangrid Power, LLC Elm Creek II Repower Application - Map 13
March 31, 2025 20253-217028-27 Avangrid Power, LLC Elm Creek II Repower Application - Map 11
March 31, 2025 20253-217028-35 Avangrid Power, LLC Elm Creek II Repower Application - Map 19
March 31, 2025 20253-217028-09 Avangrid Power, LLC Elm Creek II Repower Application - Appendix J - Part 1
March 31, 2025 20253-217028-15 Avangrid Power, LLC Elm Creek II Repower Application - Appendix N
March 31, 2025 20253-217028-14 Avangrid Power, LLC Elm Creek II Repower Application - Appendix M
March 31, 2025 20253-217028-07 Avangrid Power, LLC Elm Creek II Repower Application - Appendix G