Description

Coneflower Energy, LLC, is proposing to construct a short 345 kV high voltage transmission line in Lyon County, Minnesota

Status
active

Project Contact

Contact
Tessa Kothlow
Phone

Project Summary

Coneflower Energy, LLC (Coneflower), an independent power producer and wholly owned subsidiary of Apex Clean Energy Holdings, LLC (Apex), seek a route permit to construct the Coneflower Transmission Line Project, a short (less than a mile) 345 kV high voltage transmission line in Lyon County, Minnesota. The Coneflower Transmission Project is needed to interconnect the Coneflower Solar Project (Docket GS-24-215) to the electrical grid. The Public Utilities Commission (PUC) issued a site permit for the up to 245 MW Coneflower Solar Project on August 7, 2025. The Coneflower Solar Project was designed to have flexibility in how it provides electricity to the grid with two potential interconnection scenarios: the MISO Scenario and the Garvin Scenario. The Garvin Scenario requires a short 345 kV transmission line (Coneflower Transmission Line Project) to interconnect the Coneflower Solar Project to the electrical grid at the Xcel Energy-owned Garvin Substation. The Coneflower Transmission Line Project requires Coneflower to submit a route permit to the PUC. 

Interactive Map

Key Project Dates and Information

Key Project Documents

Date
Title
Description
May 14, 2026
NOTICE OF COMPLETE ROUTE PERMIT APPLICATION AND PUBLIC INFORMATION MEETINGS
April 30, 2026
ROUTE PERMIT APPLICATION

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
July 6, 2026 20267-233799-01 PUC
July 2, 2026 20267-233759-01 PUC Consent
July 2, 2026 20267-233739-01 PUC Proposed Consent Items
June 29, 2026 20266-233460-01 PUC Public Info Meeting Presentation
June 25, 2026 20266-233294-01 PUC Scoping Summary and Draft Permit
June 18, 2026 20266-233099-01 PUC Oral Public Comments
June 18, 2026 20266-233098-01 PUC Written Public Comments
June 18, 2026 20266-233067-01 PUC NOTICE OF PLANNING MEETING
June 16, 2026 20266-232976-01 Coneflower Energy, LLC
June 15, 2026 20266-232924-01 MN Department of Natural Resources DNR Comment Letter
June 15, 2026 20266-232879-01 MnDOT Letter
June 9, 2026 20266-232670-01 PUC Public Meeting Notice Affidavit
May 14, 2026 20265-231829-01 PUC Application Completeness Determination
May 14, 2026 20265-231805-01 PUC NOTICE OF COMPLETE ROUTE PERMIT APPLICATION AND PUBLIC INFORMATION MEETINGS
May 5, 2026 20266-233091-01 PUC Leech Lake Band of Ojibwe - Tribal Historic Preservation Officer
April 30, 2026 20264-231267-08 Coneflower Energy, LLC Appendix E Agency Correspondence PUBLIC
April 30, 2026 20264-231267-05 Coneflower Energy, LLC Appendix C Sample Route Permit
April 30, 2026 20264-231267-06 Coneflower Energy, LLC Appendix D Tribal Correspondence
April 30, 2026 20264-231267-10 Coneflower Energy, LLC Appendix G Draft Vegetation Management Plan
April 30, 2026 20264-231267-13 Coneflower Energy, LLC Appendix J GIS Data Sources
April 30, 2026 20264-231267-01 Coneflower Energy, LLC Route Permit Application Filing Cover Letter and COS
April 30, 2026 20264-231267-11 Coneflower Energy, LLC Appendix H Greenhouse Gas and Emissions Calculations
April 30, 2026 20264-231267-12 Coneflower Energy, LLC Appendix I Landowner List
April 30, 2026 20264-231267-04 Coneflower Energy, LLC Appendix B Detail Maps
April 30, 2026 20264-231267-03 Coneflower Energy, LLC Appendix A Completeness Checklist
April 30, 2026 20264-231267-02 Coneflower Energy, LLC Route Permit Application
April 30, 2026 20264-231267-09 Coneflower Energy, LLC Appendix F Response to EIP