Coneflower 345 kV Transmission Line Project

Project Details

Docket Numbers
Project Name
Coneflower 345 kV Transmission Line Project
Applicant
Coneflower Energy, LLC , Apex Clean Energy Holdings, LLC
Location
Lyon County
Description

Coneflower Energy, LLC, is proposing to construct a short 345 kV high voltage transmission line in Lyon County, Minnesota

Status
active

Project Contact

Contact
Tessa Kothlow
Phone

Project Summary

Coneflower Energy, LLC (Coneflower), an independent power producer and wholly owned subsidiary of Apex Clean Energy Holdings, LLC (Apex), seek a route permit to construct the Coneflower Transmission Line Project, a short (less than a mile) 345 kV high voltage transmission line in Lyon County, Minnesota. The Coneflower Transmission Project is needed to interconnect the Coneflower Solar Project (Docket GS-24-215) to the electrical grid. The Public Utilities Commission (PUC) issued a site permit for the up to 245 MW Coneflower Solar Project on August 7, 2025. The Coneflower Solar Project was designed to have flexibility in how it provides electricity to the grid with two potential interconnection scenarios: the MISO Scenario and the Garvin Scenario. The Garvin Scenario requires a short 345 kV transmission line (Coneflower Transmission Line Project) to interconnect the Coneflower Solar Project to the electrical grid at the Xcel Energy-owned Garvin Substation. The Coneflower Transmission Line Project requires Coneflower to submit a route permit to the PUC. 

Interactive Map

Key Project Dates and Information

Key Project Documents

Date
Title
Description
May 14, 2026
NOTICE OF COMPLETE ROUTE PERMIT APPLICATION AND PUBLIC INFORMATION MEETINGS
April 30, 2026
ROUTE PERMIT APPLICATION

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
May 14, 2026 20265-231805-01 PUC NOTICE OF COMPLETE ROUTE PERMIT APPLICATION AND PUBLIC INFORMATION MEETINGS
May 14, 2026 20265-231829-01 PUC Application Completeness Determination
April 30, 2026 20264-231267-08 Coneflower Energy, LLC Appendix E Agency Correspondence PUBLIC
April 30, 2026 20264-231267-09 Coneflower Energy, LLC Appendix F Response to EIP
April 30, 2026 20264-231267-02 Coneflower Energy, LLC Route Permit Application
April 30, 2026 20264-231267-03 Coneflower Energy, LLC Appendix A Completeness Checklist
April 30, 2026 20264-231267-04 Coneflower Energy, LLC Appendix B Detail Maps
April 30, 2026 20264-231267-12 Coneflower Energy, LLC Appendix I Landowner List
April 30, 2026 20264-231267-11 Coneflower Energy, LLC Appendix H Greenhouse Gas and Emissions Calculations
April 30, 2026 20264-231267-01 Coneflower Energy, LLC Route Permit Application Filing Cover Letter and COS
April 30, 2026 20264-231267-13 Coneflower Energy, LLC Appendix J GIS Data Sources
April 30, 2026 20264-231267-10 Coneflower Energy, LLC Appendix G Draft Vegetation Management Plan
April 30, 2026 20264-231267-06 Coneflower Energy, LLC Appendix D Tribal Correspondence
April 30, 2026 20264-231267-05 Coneflower Energy, LLC Appendix C Sample Route Permit