Mayhew Lake Energy Storage System

Project Details

Docket Numbers
Project Name
Mayhew Lake Energy Storage System
Applicant
Mayhew Lake Energy Storage, LLC
Location
Benton County
Description

A battery energy storage system with a nominal power rating of up to 100 MW alternating current with approximately 400 megawatt-hours of energy capacity on a site consisting of approximately 37 acres adjacent to the Northern States Power Mayhew Lake Substation in Sauk Rapids Township, Benton County, Minnesota

Status
active

Project Contact

Contact
Sam Weaver
Phone

Project Summary

The Applicant proposes to construct and operate a battery energy storage system with a nominal power rating of up to 100 MW alternating current with approximately 400 megawatt-hours of energy capacity on a site consisting of approximately 37 acres adjacent to the Northern States Power Mayhew Lake Substation in Sauk Rapids Township, Benton County, Minnesota. In addition to battery energy storage enclosures, the facility will also include a project substation, power conversion facilities (inverters and transformers), underground collection cables, an operations and maintenance (O&M) building, and other associated facilities, such as fencing, access roads, and stormwater basins. The project will connect to the existing Northern States Power Mayhew Lake Substation via an approximately 250-foot, 115 kilovolt (kV) transmission line. 

Key Project Documents

Date
Title
Description
06/08/2026
Site Permit Application and Environmental Assessment

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
July 22, 2026 20267-234518-01 Mayhew Lake Energy Storage, LLC Response Comments
July 22, 2026 20267-234498-01 PUC EIP Written Public Comments Received
July 22, 2026 20267-234498-02 PUC EIP Oral Comments from Public Information and Scoping Meetings
July 17, 2026 20267-234302-02 PUC Public Information Meeting_Mayhew Lake Energy Storage Sauk Rapids
July 17, 2026 20267-234302-04 PUC Public Information Meeting_Mayhew Lake Energy Storage Virtual
July 17, 2026 20267-234302-01 PUC Public Information Meeting_Mayhew Lake Energy Storage Sauk Rapids
July 17, 2026 20267-234302-03 PUC Public Information Meeting_Mayhew Lake Energy Storage Virtual
July 13, 2026 20267-234089-01 PUC Tina Douvier
July 13, 2026 20267-234073-02 Minnesota Department of Natural Resources Natural Heritage Review Letter
July 13, 2026 20267-234073-01 Minnesota Department of Natural Resources
July 13, 2026 20267-234040-01 PUC Benton Economic Partnership, Inc
July 8, 2026 20267-233936-01 PUC Rose Dyer
July 8, 2026 20267-233896-01 PUC Jennifer McLaird
July 6, 2026 20267-233805-01 PUC Presentation
June 25, 2026 20266-233305-01 PUC Sample BESS Permit
June 18, 2026 20266-233067-01 PUC NOTICE OF PLANNING MEETING
June 15, 2026 20266-233211-01 Mayhew Lake Energy Storage, LLC Benton County Herald
June 15, 2026 20266-233211-02 Mayhew Lake Energy Storage, LLC St. Cloud Times
June 15, 2026 20266-232702-01 PUC NOTICE OF COMPLETE SITE PERMIT APPLICATION AND PUBLIC INFORMATION MEETINGS
June 11, 2026 20266-232798-01 PUC EIP Application Completeness Determinations
June 1, 2026 20266-232403-01 Mayhew Lake Energy Storage, LLC Site Permit Application
June 1, 2026 20266-232403-09 Mayhew Lake Energy Storage, LLC Site Permit Application - Appendix H - PUBLIC
June 1, 2026 20266-232403-07 Mayhew Lake Energy Storage, LLC Site Permit Application - Appendix F
June 1, 2026 20266-232403-05 Mayhew Lake Energy Storage, LLC Site Permit Application - Appendix D
June 1, 2026 20266-232403-12 Mayhew Lake Energy Storage, LLC Site Permit Application - Appendix J
June 1, 2026 20266-232403-08 Mayhew Lake Energy Storage, LLC Site Permit Application - Appendix G
June 1, 2026 20266-232403-04 Mayhew Lake Energy Storage, LLC Site Permit Application - Appendix C
June 1, 2026 20266-232403-15 Mayhew Lake Energy Storage, LLC Site Permit Application - Appendix M
June 1, 2026 20266-232403-03 Mayhew Lake Energy Storage, LLC Site Permit Application - Appendix B
June 1, 2026 20266-232403-02 Mayhew Lake Energy Storage, LLC Site Permit Application - Appendix A