Description
Xcel Energy's proposal for a battery energy storage system on a site adjacent to the Sherburne County Generating Station in the City of Becker, Sherburne County.
Status
active
Project Contact
Project Summary
Xcel Energy proposes to construct and operate a battery energy storage system with a nominal power rating of up to 600 megawatts (MW) alternating current with approximately 2,400 megawatt-hours of energy capacity on a site consisting of approximately 60 acres adjacent to the Sherburne County Generating Station in the City of Becker, Sherburne County, Minnesota
Interactive Map
Key Project Documents
Date
|
Title
|
Description
|
|---|---|---|
02/27/2026
|
Notice of Public Hearings and Availability of Draft Permit
|
|
12/22/2025
|
Notice of Site Permit Application Completeness Determination and Public Information Meetings
|
|
12/22/2025
|
Application for Site Permit
|
Docket Documents
View Project Documents (last 30) View All Project Documents
| Date | Document ID | On Behalf Of | Description |
|---|---|---|---|
| June 29, 2026 | 20266-233487-04 | Xcel Energy | Section 4.5.2 |
| June 29, 2026 | 20266-233487-01 | Xcel Energy | Section 9.1 Updated Decomm Plan |
| June 29, 2026 | 20266-233487-05 | Xcel Energy | Section 4.4 Site Plan |
| June 29, 2026 | 20266-233487-03 | Xcel Energy | Section 5.7 Tree Replmnt |
| June 29, 2026 | 20266-233487-06 | Xcel Energy | Section 8.3 Site Permit Distribution |
| June 29, 2026 | 20266-233487-07 | Xcel Energy | Section 4.1 Site Permit Distributio |
| June 29, 2026 | 20266-233487-02 | Xcel Energy | Section 8.11Emergency Response |
| June 25, 2026 | 20266-233313-01 | Xcel Energy | Section 4.3.1- Field Representative |
| June 25, 2026 | 20266-233313-03 | Xcel Energy | Section 5.1 Vegetation Management Plan |
| June 25, 2026 | 20266-233313-05 | Xcel Energy | Section 5.3 Noise Study |
| June 25, 2026 | 20266-233313-04 | Xcel Energy | Section 5.2 Pre-Construction Noise |
| June 25, 2026 | 20266-233313-02 | Xcel Energy | Section 4.3.27 Public Safety |
| June 23, 2026 | 20266-233198-01 | Xcel Energy | Section 4.3.17 Invasive Species |
| June 23, 2026 | 20266-233200-01 | Xcel Energy | Section 5.10 NHIS Resubmittal |
| June 23, 2026 | 20266-233206-01 | Xcel Energy | Section 7_Complaint Procedures |
| June 22, 2026 | 20266-233137-01 | Xcel Energy | Section 4.3.16 Application for Pesticides |
| June 22, 2026 | 20266-233133-01 | Xcel Energy | Section 4.3.4 Independent Enviromental Monitoring |
| June 22, 2026 | 20266-233134-01 | Xcel Energy | Section 4.3.14 Native Prairie |
| June 22, 2026 | 20266-233152-01 | Xcel Energy | Section 5.9 Security Fence |
| June 18, 2026 | 20266-233095-01 | Xcel Energy | Project Ownership |
| June 18, 2026 | 20266-233067-01 | PUC | NOTICE OF PLANNING MEETING |
| June 18, 2026 | 20266-233059-01 | PUC | NOTICE OF PLANNING MEETING - FILED IN ERROR |
| June 15, 2026 | 20266-232938-01 | Xcel Energy | Hazard Mitigation Analysis |
| June 11, 2026 | 20266-232787-01 | PUC | |
| June 2, 2026 | 20266-232466-01 | PUC | Received Outside Comment Period- Tom Mosby - FILED IN ERROR |
| May 13, 2026 | 20265-231784-01 | PUC | May 21, 2026 Agenda |
| May 8, 2026 | 20265-231529-01 | PUC | May 21, 2026 Agenda |
| May 1, 2026 | 20265-231328-01 | CAH | Summary of Public Comments |
| April 6, 2026 | 20264-230073-01 | Xcel Energy | Response to Public Comments and Proposed FOF |
| April 2, 2026 | 20264-229946-01 | PUC | EIP Staff Comments |