Otto Tap 115 kV Transmission Project

Project Details

Docket Numbers
Project Name
Otto Tap 115 kV Transmission Project
Applicant
Great River Energy and Lake Region Electric Cooperative
Location
Otter Tail County
Description

Great River Energy and Lake Region Electric Cooperative propose to build a new 2.9-mile 115-kilovolt single-circuit high voltage transmission line and a new Otto Substation in Otter Tail County, Minnesota.

Status
active

Project Contact

Contact
Suzanne Steinhauer
Phone

Project Summary

Great River Energy and Lake Region Electric Cooperative (applicants) seek a route permit to construct and operate the Otto Tap Project (project) in Otto and Pine Lake townships in Otter Tail County, Minnesota. The project will consist of approximately 2.9 miles of new single-circuit 115 kilovolt (kV) transmission line between Great River Energy’s 115-kV Perham to Rush Lake transmission line and a new Otto Substation that will replace Lake Region Electric Cooperative’s existing Otto Substation. The transmission line will be constructed and owned by Great River Energy. The new Otto Substation will be constructed, owned, and operated by Lake Region Electric Cooperative. The applicants indicate that the project is needed ensure reliable service by upgrading the Otto Substation with a connection to the 115-kV transmission system. The applicants propose to begin construction of the project in late 2027 and for the project to be in service by the summer of 2028.

Interactive Map

Key Project Dates and Information

Key Project Documents

Date
Title
Description
11/03/2025
The application for the Otto Tap 115 kV transmission project in Otter Tail County proposed by Great River Energy and Lake Region Electric Cooperative. For all application appendices, go to eDockets via the link below: “View All Project Documents."

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
November 20, 2025 202511-225134-01 PUC Sample HVTL Permit
November 18, 2025 202511-225028-01 PUC NOTICE OF COMPLETE ROUTE PERMIT APPLICATION AND PUBLIC INFORMATION MEETINGS
November 18, 2025 202511-225016-01 PUC NOTICE OF COMPLETE ROUTE PERMIT APPLICATION AND PUBLIC INFORMATION MEETINGS - FILED IN ERROR
November 18, 2025 202511-225019-01 PUC Application Completeness
November 3, 2025 202511-224627-10 Great River Energy and Lake Region Electric Cooperative Appendix D - Tribal Correspondence - Part 4 of 4
November 3, 2025 202511-224627-02 Great River Energy and Lake Region Electric Cooperative Route Permit Application
November 3, 2025 202511-224627-01 Great River Energy and Lake Region Electric Cooperative Application Filing Letter
November 3, 2025 202511-224627-14 Great River Energy and Lake Region Electric Cooperative Appendix H - GHG Emission Calculations
November 3, 2025 202511-224627-08 Great River Energy and Lake Region Electric Cooperative Appendix D - Tribal Correspondence - Part 2 of 4
November 3, 2025 202511-224627-04 Great River Energy and Lake Region Electric Cooperative Appendix B - Detailed Maps
November 3, 2025 202511-224627-03 Great River Energy and Lake Region Electric Cooperative Appendix A - Application Checklist
November 3, 2025 202511-224627-12 Great River Energy and Lake Region Electric Cooperative Appendix F - List of Landowners
November 3, 2025 202511-224627-07 Great River Energy and Lake Region Electric Cooperative Appendix D - Tribal Correspondence - Part 1 of 4
November 3, 2025 202511-224627-09 Great River Energy and Lake Region Electric Cooperative Appendix D - Tribal Correspondence - Part 3 of 4
November 3, 2025 202511-224627-05 Great River Energy and Lake Region Electric Cooperative Appendix C - Agency Correspondence
November 3, 2025 202511-224627-13 Great River Energy and Lake Region Electric Cooperative Appendix G - DVMP
November 3, 2025 202511-224627-11 Great River Energy and Lake Region Electric Cooperative Appendix E - MPUC 9.25.35 Draft Application Review Comments and Applicants' Response