Otto Tap 115 kV Transmission Project

Project Details

Docket Numbers
Project Name
Otto Tap 115 kV Transmission Project
Applicant
Great River Energy and Lake Region Electric Cooperative
Location
Otter Tail County
Description

Great River Energy and Lake Region Electric Cooperative propose to build a new 2.9-mile 115-kilovolt single-circuit high voltage transmission line and a new Otto Substation in Otter Tail County, Minnesota.

Status
active

Project Contact

Contact
Suzanne Steinhauer
Phone

Project Summary

Great River Energy and Lake Region Electric Cooperative (applicants) seek a route permit to construct and operate the Otto Tap Project (project) in Otto and Pine Lake townships in Otter Tail County, Minnesota. The project will consist of approximately 2.9 miles of new single-circuit 115 kilovolt (kV) transmission line between Great River Energy’s 115-kV Perham to Rush Lake transmission line and a new Otto Substation that will replace Lake Region Electric Cooperative’s existing Otto Substation. The transmission line will be constructed and owned by Great River Energy. The new Otto Substation will be constructed, owned, and operated by Lake Region Electric Cooperative. The applicants indicate that the project is needed ensure reliable service by upgrading the Otto Substation with a connection to the 115-kV transmission system. The applicants propose to begin construction of the project in late 2027 and for the project to be in service by the summer of 2028.

Interactive Map

Key Project Documents

Date
Title
Description
01/013/2026
Otto Tap Draft Route Permit Order
12/01/2025
Notice of Public Meeting and Comment Period
11/03/2025
The application for the Otto Tap 115 kV transmission project in Otter Tail County proposed by Great River Energy and Lake Region Electric Cooperative. For all application appendices, go to eDockets via the link below: “View All Project Documents."
01/20/2026
Notice of Public Hearings and Availability of Draft Permit

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
February 23, 2026 20262-228458-01 Great River Energy Public Hearings
February 19, 2026 20262-228385-01 MN Department of Natural Resources DNR Comment Letter
February 19, 2026 20262-228389-01 Minnesota Interagency Vegetation Management Planning Working Group VMPWG Hearing Comments
February 18, 2026 20262-228304-01 PUC EQB Monitor Hearing Publication
February 18, 2026 20262-228277-01 Great River Energy Comments on Draft Route Permit
February 3, 2026 20262-227792-01 PUC Public Hearing Slides
January 16, 2026 20261-227007-01 PUC NOTICE OF PUBLIC HEARINGS AND AVAILABILITY OF DRAFT PERMIT
January 13, 2026 20261-226806-01 CAH First Prehearing Order
January 9, 2026 20261-226796-01 Shaddix & Associates - Stenographic Court Reporters Prehearing held on 1-9-26
January 9, 2026 20261-226681-01 PUC
January 8, 2026 20261-226649-01 PUC January 8, 2026 Consent
January 8, 2026 20261-226615-01 PUC Proposed Consent Items
January 7, 2026 20261-226587-01 PUC EIP EIP Staff Recommendations on Draft Route Permit and Need for Environmental Assessment Addendum
January 7, 2026 20261-226581-01 CAH Order for Prehearing Conference
December 19, 2025 202512-226032-01 PUC Otter Tail County Comment
December 18, 2025 202512-225990-01 PUC Otto Tap Public Info Meeting - Newspaper Affidavits
December 17, 2025 202512-225980-02 PUC Comments from New York Mills Public Information and Scoping Meeting for Otto Tap 115 kV Transmission Line Project
December 17, 2025 202512-225980-01 PUC Comments from Virtual Public Information and Scoping Meeting for Otto Tap 115 kV Transmission Line Project
December 2, 2025 202512-225469-01 PUC EQB Notice - Public Information Meeting
December 2, 2025 202512-225448-01 Great River Energy and Lake Region Electric Cooperative 2025-12-02 Otto Tap - Supplemental Filing re Completeness Determination
November 20, 2025 202511-225134-01 PUC Sample HVTL Permit
November 18, 2025 202511-225028-01 PUC NOTICE OF COMPLETE ROUTE PERMIT APPLICATION AND PUBLIC INFORMATION MEETINGS
November 18, 2025 202511-225016-01 PUC NOTICE OF COMPLETE ROUTE PERMIT APPLICATION AND PUBLIC INFORMATION MEETINGS - FILED IN ERROR
November 18, 2025 202511-225019-01 PUC Application Completeness
November 3, 2025 202511-224627-11 Great River Energy and Lake Region Electric Cooperative Appendix E - MPUC 9.25.35 Draft Application Review Comments and Applicants' Response
November 3, 2025 202511-224627-04 Great River Energy and Lake Region Electric Cooperative Appendix B - Detailed Maps
November 3, 2025 202511-224627-13 Great River Energy and Lake Region Electric Cooperative Appendix G - DVMP
November 3, 2025 202511-224627-05 Great River Energy and Lake Region Electric Cooperative Appendix C - Agency Correspondence
November 3, 2025 202511-224627-09 Great River Energy and Lake Region Electric Cooperative Appendix D - Tribal Correspondence - Part 3 of 4
November 3, 2025 202511-224627-07 Great River Energy and Lake Region Electric Cooperative Appendix D - Tribal Correspondence - Part 1 of 4