Otto Tap 115 kV Transmission Project
Project Details
Great River Energy and Lake Region Electric Cooperative propose to build a new 2.9-mile 115-kilovolt single-circuit high voltage transmission line and a new Otto Substation in Otter Tail County, Minnesota.
Project Contact
Project Summary
Great River Energy and Lake Region Electric Cooperative (applicants) seek a route permit to construct and operate the Otto Tap Project (project) in Otto and Pine Lake townships in Otter Tail County, Minnesota. The project will consist of approximately 2.9 miles of new single-circuit 115 kilovolt (kV) transmission line between Great River Energy’s 115-kV Perham to Rush Lake transmission line and a new Otto Substation that will replace Lake Region Electric Cooperative’s existing Otto Substation. The transmission line will be constructed and owned by Great River Energy. The new Otto Substation will be constructed, owned, and operated by Lake Region Electric Cooperative. The applicants indicate that the project is needed ensure reliable service by upgrading the Otto Substation with a connection to the 115-kV transmission system. The applicants propose to begin construction of the project in late 2027 and for the project to be in service by the summer of 2028.
Interactive Map
Key Project Dates and Information
Key Project Documents
Date
|
Title
|
Description
|
|---|---|---|
11/03/2025
|
The application for the Otto Tap 115 kV transmission project in Otter Tail County proposed by Great River Energy and Lake Region Electric Cooperative. For all application appendices, go to eDockets via the link below: “View All Project Documents."
|
Docket Documents
View Project Documents (last 30) View All Project Documents
| Date | Document ID | On Behalf Of | Description |
|---|---|---|---|
| November 20, 2025 | 202511-225134-01 | PUC | Sample HVTL Permit |
| November 18, 2025 | 202511-225028-01 | PUC | NOTICE OF COMPLETE ROUTE PERMIT APPLICATION AND PUBLIC INFORMATION MEETINGS |
| November 18, 2025 | 202511-225016-01 | PUC | NOTICE OF COMPLETE ROUTE PERMIT APPLICATION AND PUBLIC INFORMATION MEETINGS - FILED IN ERROR |
| November 18, 2025 | 202511-225019-01 | PUC | Application Completeness |
| November 3, 2025 | 202511-224627-10 | Great River Energy and Lake Region Electric Cooperative | Appendix D - Tribal Correspondence - Part 4 of 4 |
| November 3, 2025 | 202511-224627-02 | Great River Energy and Lake Region Electric Cooperative | Route Permit Application |
| November 3, 2025 | 202511-224627-01 | Great River Energy and Lake Region Electric Cooperative | Application Filing Letter |
| November 3, 2025 | 202511-224627-14 | Great River Energy and Lake Region Electric Cooperative | Appendix H - GHG Emission Calculations |
| November 3, 2025 | 202511-224627-08 | Great River Energy and Lake Region Electric Cooperative | Appendix D - Tribal Correspondence - Part 2 of 4 |
| November 3, 2025 | 202511-224627-04 | Great River Energy and Lake Region Electric Cooperative | Appendix B - Detailed Maps |
| November 3, 2025 | 202511-224627-03 | Great River Energy and Lake Region Electric Cooperative | Appendix A - Application Checklist |
| November 3, 2025 | 202511-224627-12 | Great River Energy and Lake Region Electric Cooperative | Appendix F - List of Landowners |
| November 3, 2025 | 202511-224627-07 | Great River Energy and Lake Region Electric Cooperative | Appendix D - Tribal Correspondence - Part 1 of 4 |
| November 3, 2025 | 202511-224627-09 | Great River Energy and Lake Region Electric Cooperative | Appendix D - Tribal Correspondence - Part 3 of 4 |
| November 3, 2025 | 202511-224627-05 | Great River Energy and Lake Region Electric Cooperative | Appendix C - Agency Correspondence |
| November 3, 2025 | 202511-224627-13 | Great River Energy and Lake Region Electric Cooperative | Appendix G - DVMP |
| November 3, 2025 | 202511-224627-11 | Great River Energy and Lake Region Electric Cooperative | Appendix E - MPUC 9.25.35 Draft Application Review Comments and Applicants' Response |