Gopher to Badger Link

Project Details

Docket Numbers
Project Name
Gopher to Badger Link
Applicant
Xcel Energy, Dairyland Power Cooperative
Location
Description

A Certificate of Need Application has been filed by Xcel Energy and Dairyland Power Cooperative for the proposed Gopher to Badger Link Project. The Gopher to Badger Link Project would involve constructing two new 765-kV high-voltage electric transmission lines across Minnesota as part of a broader proposed regional transmission network connecting Minnesota, South Dakota, Iowa, and Wisconsin.

Status
active

Project Contact

Contact
Logan Hicks
Phone

Project Summary

In Minnesota, the Gopher to Badger Link Project would include 2 segments: 1. Segment 1: A single-circuit 765 kV high voltage transmission line that would be approximately 34 miles between the existing North Rochester Substation1 and a point near Marion, Minnesota. This portion of the route will use lattice structures to support the transmission line, which will be placed 1,100 to 1,300 feet apart, will typically be 150 to 175 feet tall, and will generally require a 250-foot-wide right-of-way. 2. Segment 2: A 765 kV/161 kV double-circuit high voltage transmission line that would be approximately 105 miles from near Marion, Minnesota, to the Wisconsin border. Segment 2 also includes a new three-circuit breaker 161 kV switching station at a location to be identified in Houston County, Minnesota, as well as minor upgrades at existing 161 kV substations to support operation of the new Project facilities. This portion of the route will use lattice structures to support the transmission line which will be placed 1,200 to 1,500 feet apart, and will typically be 150 to 199 feet tall, and will generally require a 250-foot-wide right-of-way. 

 

Interactive Map

Key Project Documents

Date
Title
Description
2/10/2026
Certificate of Need Application

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
April 6, 2026 20264-230061-01 PUC Decision Option Commissioner Tuma 11A
April 1, 2026 20264-229861-01 PUC April 9, 2026 Agenda
March 27, 2026 20263-229603-01 PUC April 9, 2026 Agenda Meeting
March 24, 2026 20263-229584-01 PUC Received Outside Commetn Period - Keefe Farms LLC
March 20, 2026 20263-229515-01 The North Route Group and NO765MN Requested Clarification - NRG and NO765MN to Applicants 117 and 121
March 19, 2026 20263-229454-01 Xcel Energy and Dairyland Power Cooperative Gopher to Badger_Filing Letter_with Response to Petition to Intervene etc
March 11, 2026 20263-229145-01 Xcel Energy and Dairyland Power Cooperative Gopher to Badger Status Update Letter
March 10, 2026 20263-229099-01 DOC DER replaces submission 20263-228992
March 10, 2026 20263-229084-01 PUC Ken Johnston
March 9, 2026 20263-229071-03 North Route Group and NO765LINE NRG and NO765MN Request for Contested Case and Joint Hearing
March 9, 2026 20263-229071-01 North Route Group and NO765LINE NRG and NO765MN Supplemental Comment Cover & Cert of Srv
March 9, 2026 20263-229071-02 North Route Group and NO765LINE NRG and NO765 Supplemental Comment - Consolidation - Discovery
March 9, 2026 20263-229071-04 North Route Group and NO765LINE NRG and NO765MN Petition for Intervention
March 9, 2026 20263-229073-01 DOC DER FILED IN ERROR
March 9, 2026 20263-229062-01 Xcel Energy and Dairyland Power Cooperative GTBL_Filing Letter with Completeness Supplemental Comments
March 9, 2026 20263-229056-01 LIUNA Minnesota/North Dakota
March 8, 2026 20263-229037-01 Trevor Scrabeck
March 6, 2026 20263-228992-01 PUC Dale Thomforde
March 5, 2026 20263-228974-01 US Fish and Wildlife Service
March 5, 2026 20263-228971-01 City of Spring Grove
March 5, 2026 20263-228957-01 PUC Batch- 10 Comments 03052026
March 4, 2026 20263-228909-01 PUC Dayva Goetzinger
March 4, 2026 20263-228895-01 Tom Hammell
March 4, 2026 20263-228896-01 PUC Josh Goetzinger
March 4, 2026 20263-228907-01 Charles Wray Contested Facts
March 4, 2026 20263-228910-01 Deborah Wray Deborah Wray
March 4, 2026 20263-228935-01 Amanda Ninneman
March 4, 2026 20263-228946-01 North Route Group and NO765MN Reply Comment of NRG and NO765MN
March 4, 2026 20263-228942-01 Xcel Energy and Dairyland Power Cooperative Gopher to Badger Filing Letter with Completeness Reply Comments
March 4, 2026 20263-228924-01 Bonnie Giesler