PowerOn Midwest

Project Details

Docket Numbers
Project Name
PowerOn Midwest
Applicant
Great River Energy, ITC Midwest LLC, and Xcel Energy
Location
Description

Project proposes building new high-voltage electric transmission lines (765 kV and 345 kV) across Minnesota as part of a larger 3,600-mile regional transmission network spanning the Midwest and the eastern United States.

Status
active

Project Contact

Contact
Scott Ek
Phone

Project Summary

The project is part of Midcontinent Independent System Operator (MISO) Long Range Transmission Planning (LRTP) Tranche 2.1 projects, approved in July 2024 under the MISO Transmission Expansion Plan 2024 (MTEP24).

MISO and the applicants have identified a need for up to 10,000 megawatts of additional electrical transmission capacity in Minnesota. As described in the Certificate of Need application and MTEP24, the project is intended to:

  • Address projected reliability overloads and support compliance with national electric reliability standards
  • Improve efficiency in meeting current and future reliability needs
  • Provide capacity to serve forecasted residential, commercial, and industrial demand, supporting long-term growth
  • Support the transition from fossil-fuel generation to carbon-free energy resources while maintaining system reliability

Interactive Map

Key Project Documents

Date
Title
Description
03/16/2026
Certificate of Need Application

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
August 14, 2026 20268-235366-01 Carol Green
August 14, 2026 20268-235293-01 PUC Joseph Risacher
August 14, 2026 20268-235294-01 PUC Frankie Socash
August 14, 2026 20268-235295-01 PUC Larry Vogel
August 14, 2026 20268-235297-01 PUC Marcela Vogel
August 14, 2026 20268-235300-01 PUC Colter Lenz
August 14, 2026 20268-235301-01 PUC Mark Ahlers
August 14, 2026 20268-235302-01 PUC Kevin Schettler
August 14, 2026 20268-235303-01 PUC Ann Kremer-Bastian
August 14, 2026 20268-235305-01 PUC Chuck and Laurie Hill
August 14, 2026 20268-235307-01 PUC Brian Crowley
August 14, 2026 20268-235309-01 PUC Dianne Crowley
August 14, 2026 20268-235311-01 PUC Mike Ahlschlager
August 14, 2026 20268-235312-01 PUC Dale Kremer
August 14, 2026 20268-235313-01 PUC Bob and Trudy Biegler
August 14, 2026 20268-235314-01 PUC Debra Kremer
August 14, 2026 20268-235056-03 PUC Outside of Comment Period - Ufer, Jay
August 14, 2026 20268-235383-01 PUC Julie Short
August 14, 2026 20268-235306-01 PUC Ben Truesdell
August 13, 2026 20268-235252-09 Great River Energy, Xcel Energy, and ITC Midwest LLC Direct Testimony of Jason Standing and Schedule 1
August 13, 2026 20268-235252-11 Great River Energy, Xcel Energy, and ITC Midwest LLC Direct Testimony of Matthew Ellis and Schedules 1-3
August 13, 2026 20268-235250-03 DOC Park Direct and Attachments
August 13, 2026 20268-235250-02 DOC Hicks Direct and Attachments
August 13, 2026 20268-235250-01 DOC Direct testimony cover letter
August 13, 2026 20268-235251-01 Great River Energy, Xcel Energy, and ITC Midwest LLC Motion for Reconsideration of Scoping Decision
August 13, 2026 20268-235235-04 PUC Art Weinrebe -Outside Comment Period
August 13, 2026 20268-235235-01 PUC Marlene Reisdorfer -Outside Comment Period
August 13, 2026 20268-235235-03 PUC Linda Brockberg -Outside Comment Period
August 13, 2026 20268-235249-01 Midcontinent Independent System Operator, Inc. Furnish Direct Testimony
August 13, 2026 20268-235235-02 PUC Maria Ahlers -Outside Comment Period