Iron Range - St. Louis County - Arrowhead 345kV Transmission Line Project

Project Details

Docket Numbers
Project Name
Iron Range - St. Louis County - Arrowhead 345kV Transmission Line Project
Applicant
Minnesota Power and American Transmission Company, LLC
Location
St. Louis County
Description

Minnesota Power and American Transmission Company, LLC propose to construct approximately 67.5 miles of transmission line from Minnesota Power's Iron Range Substation near Grand Rapids, Minnesota to Minnesota Power's St. Louis County Substation near Hermantown, Minnesota, with a connection to American Transmission Company's nearby Arrowhead Substation along portions of Itasca and St. Louis Counties. The route proposed is located along, and in some cases replaces, existing high-voltage transmission lines for 92 percent of its length. New transmission lines will be required to connect the existing substations in Grand Rapids and Hermantown. Existing substations would also require expansions.

Status
active

Project Contact

Contact
Emily Johnson

Project Summary

Minnesota Power and American Transmission Company, LLC (ATC) propose to construct approximately 67.5 miles of transmission line from Minnesota Power's Iron Range Substation near Grand Rapids, Minnesota to Minnesota Power's St. Louis County Substation near Hermantown, Minnesota, with a connection to American Transmission Company's nearby Arrowhead Substation along portions of Itasca and St. Louis Counties. The project is needed to provide additional transmission capacity, mitigate current capacity issues, and improve electric system reliability. The proposed project includes three segments. Segment one consists of 32.7 miles of new 345 kV line along existing HVTL ROW from the Iron Range Substation to the north of the St. Louis River in St. Louis County. Segment two would replace approximately 33.3 miles of existing 230 kV HVTL with 345 kV HVTL from north of the St. Louis River in St. Louis County to Minnesota Power's St. Louis County Substation in Solway Township. Segment three consists of 1.5 miles of new 345 kV HVTL from St. Louis County Substation to the ATC Arrowhead Substation in Hermantown, Minnesota. The Iron Range - St. Louis County - Arrowhead 345kV Transmission Line Project will also require a certificate of need (CN-25-111). 

Comment on this project

To comment on this project and learn more about how to make an effective comment, go here

Interactive Map

Key Project Dates and Information

Key Project Documents

Date
Title
Description
06/11/2026
NOTICE OF COMMENT PERIOD ON THE MERITS OF THE CERTIFICATE OF NEED APPLICATION
03/12/2026
Notice of Complete Application and Rescheduled Public Information and Scoping Meetings
03/22/2026
New Notice of Comment Period
02/06/2025
Notice of Cancellation of Public Meetings
01/22/2026
NOTICE OF COMPLETE APPLICATION AND PUBLIC INFORMATION AND SCOPING MEETINGS
01/06/2026
Combined Application and Appendices A through D

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
July 16, 2026 20267-234239-01 PUC Emily Rakos
July 15, 2026 20267-234205-01 North Route Group and NO765MN NRG & NO765MN Comment on Data Centers and Tranche 2.1 Transmission
July 13, 2026 20267-234084-01 DOC DER
July 13, 2026 20267-234062-01 World Organization for Landowner Freedom Initial CoN Comment - World Organization for Landowner Freedom
July 13, 2026 20267-234061-01 Fresh Energy/CGA Initial Comments on the Merits of the Certificate of Need Application
July 13, 2026 20267-234060-01 Midcontinent Independent System Operator, Inc.
July 13, 2026 20267-234062-01 World Organization for Landowner Freedom Initial CoN Comment - World Organization for Landowner Freedom
July 13, 2026 20267-234042-01 PUC Jeanne Fahlstrom
July 13, 2026 20267-234042-02 PUC Joycanne Hoyem
July 13, 2026 20267-234043-01 PUC Barbara Opal
July 13, 2026 20267-234043-02 PUC Linda Forsyth
July 13, 2026 20267-234042-02 PUC Joycanne Hoyem
July 13, 2026 20267-234042-01 PUC Jeanne Fahlstrom
July 13, 2026 20267-234044-01 PUC Tina Douvier
July 10, 2026 20267-234001-01 PUC LETTER TO ALTERNATIVE LANDOWNERS
July 10, 2026 20267-234001-01 PUC LETTER TO ALTERNATIVE LANDOWNERS
July 9, 2026 20267-233951-01 PUC Tim Tapani
July 9, 2026 20267-233951-01 PUC Tim Tapani
July 8, 2026 20267-233929-01 PUC Charlie Martin
July 8, 2026 20267-233929-02 PUC Debra Thorstensen
July 8, 2026 20267-233930-01 PUC Charlie Martin
July 8, 2026 20267-233891-01 PUC Tim & Jessica Tapani
July 8, 2026 20267-233894-01 PUC Linda Herron
July 8, 2026 20267-233892-01 PUC Martinique Williams
July 8, 2026 20267-233891-01 PUC Tim & Jessica Tapani
July 2, 2026 20267-233767-01 CAH Prehearing Order
July 2, 2026 20267-233767-01 CAH Prehearing Order
July 2, 2026 20267-233779-01 Carol A. Overland and World Organization for Landowner Freedom Second Affidavit of Disqualification
July 2, 2026 20267-233779-01 Carol A. Overland and World Organization for Landowner Freedom Second Affidavit of Disqualification
July 1, 2026 20267-233654-01 PUC