Iron Range - St. Louis County - Arrowhead 345kV Transmission Line Project
Project Details
Minnesota Power and American Transmission Company, LLC propose to construct approximately 67.5 miles of transmission line from Minnesota Power's Iron Range Substation near Grand Rapids, Minnesota to Minnesota Power's St. Louis County Substation near Hermantown, Minnesota, with a connection to American Transmission Company's nearby Arrowhead Substation along portions of Itasca and St. Louis Counties. The route proposed is located along, and in some cases replaces, existing high-voltage transmission lines for 92 percent of its length. New transmission lines will be required to connect the existing substations in Grand Rapids and Hermantown. Existing substations would also require expansions.
Project Contact
Project Summary
Minnesota Power and American Transmission Company, LLC (ATC) propose to construct approximately 67.5 miles of transmission line from Minnesota Power's Iron Range Substation near Grand Rapids, Minnesota to Minnesota Power's St. Louis County Substation near Hermantown, Minnesota, with a connection to American Transmission Company's nearby Arrowhead Substation along portions of Itasca and St. Louis Counties. The project is needed to provide additional transmission capacity, mitigate current capacity issues, and improve electric system reliability. The proposed project includes three segments. Segment one consists of 32.7 miles of new 345 kV line along existing HVTL ROW from the Iron Range Substation to the north of the St. Louis River in St. Louis County. Segment two would replace approximately 33.3 miles of existing 230 kV HVTL with 345 kV HVTL from north of the St. Louis River in St. Louis County to Minnesota Power's St. Louis County Substation in Solway Township. Segment three consists of 1.5 miles of new 345 kV HVTL from St. Louis County Substation to the ATC Arrowhead Substation in Hermantown, Minnesota. The Iron Range - St. Louis County - Arrowhead 345kV Transmission Line Project will also require a certificate of need (CN-25-111).
Interactive Map
Key Project Documents
Date
|
Title
|
Description
|
|---|---|---|
Docket Documents
View Project Documents (last 30) View All Project Documents
| Date | Document ID | On Behalf Of | Description |
|---|---|---|---|
| November 19, 2025 | 202511-225066-01 | Minnesota Power and American Transmission Company | Request to Approve Project Notice Area Map |
| November 18, 2025 | 202511-225041-01 | PUC | |
| November 10, 2025 | 202511-224783-01 | Minnesota Power and American Transmission Company | Sixth Status Update |
| October 28, 2025 | 202510-224356-01 | PUC | October 30, 2025 Agenda - Decision Option - Commissioner Tuma |
| October 20, 2025 | 202510-224102-01 | PUC | October 30, 2025 Agenda |
| October 17, 2025 | 202510-223993-01 | PUC | October 30, 2025 Agenda |
| October 6, 2025 | 202510-223617-01 | DOC DER | |
| September 26, 2025 | 20259-223334-01 | Minnesota Power and American Transmission Company | Fifth Status Update |
| September 16, 2025 | 20259-223087-03 | Minnesota Power and American Transmission Company | Certificate of Service - Reply Comments |
| September 16, 2025 | 20259-223087-01 | Minnesota Power and American Transmission Company | Reply Comments on Request for Exemptions |
| September 16, 2025 | 20259-223087-02 | Minnesota Power and American Transmission Company | Reply Comments on Notice Plan Petition |
| August 27, 2025 | 20258-222450-02 | DOC DER | on Exemption Request |
| August 27, 2025 | 20258-222486-01 | No CapX 2020 and WOLF | Comments of No CapX 2020 and WOLF |
| August 27, 2025 | 20258-222450-01 | DOC DER | on Notice Plan |
| August 19, 2025 | 20258-222214-01 | PUC | NOTICE OF COMMENT PERIOD ON REQUEST FOR EXEMPTION FROM CERTAIN CERTIFICATE OF NEED APPLICATION CONTENT REQUIREMENTS |
| August 14, 2025 | 20258-222064-01 | Minnesota Power and American Transmission Company | Fourth Status Update |
| August 7, 2025 | 20258-221879-01 | Minnesota Power and American Transmission Company LLC | Request for Exemptions |
| August 7, 2025 | 20258-221885-01 | Minnesota Power and American Transmission Company LLC | Notice Plan Petition |
| June 30, 2025 | 20256-220458-01 | Minnesota Power and American Transmission Company | Third Status Update |
| May 16, 2025 | 20255-219010-01 | Minnesota Power and American Transmission Company | Second Status Update (Iron Range - St. Louis County - Arrowhead) |
| April 3, 2025 | 20254-217216-01 | Minnesota Power and American Transmission Company | Iron Range - St. Louis - Arrowhead First Status Report |
| March 4, 2025 | 20253-216012-01 | PUC | Status Update |
| March 4, 2025 | 20253-216012-01 | PUC | Status Update |
| February 7, 2025 | 20252-215075-01 | Minnesota Power | Notice of Intent |
| February 7, 2025 | 20252-215075-01 | Minnesota Power | Notice of Intent |