Blue Lake Battery Energy Storage Project

Project Details

Docket Numbers
Project Name
Blue Lake Battery Energy Storage Project
Applicant
Xcel Energy
Location
Scott County
Description

Xcel Energy proposes to construct and operate a battery energy storage system with a nominal power rating of up to 135.5 megawatts (MW) alternating current with approximately 542 megawatt-hours of energy capacity on a site consisting of approximately 70 acres adjacent to Xcel Energy's existing Blue Lake Peaking Plant in the City of Shakopee, Scott County, Minnesota

Status
active

Project Contact

Contact
Suzanne Steinhauer
Phone

Project Summary

Interactive Map

Docket Documents

View All Project Documents 

Date Title On Behalf Of Description
August 12, 2025 20258-221987-01 PUC
August 11, 2025 20258-221962-01 PUC Consent
August 7, 2025 20258-221864-01 PUC Proposed Consent Items
July 24, 2025 20257-221378-01 PUC EIP on Application Completeness
July 18, 2025 20257-221145-01 Xcel Energy Completeness Reply Comments
July 16, 2025 20257-221068-01 Xcel Energy Confirmation of Notice
July 11, 2025 20257-220856-01 IUOE Local 49 and NCSRC of Carpenters
July 11, 2025 20257-220868-01 PUC EIP Staff Comments
July 9, 2025 20257-220799-01 PUC Notice of Legislative Changes
June 27, 2025 20256-220363-01 PUC NOTICE OF COMMENT PERIOD ON APPLICATION COMPLETENESS
June 23, 2025 20256-220142-01 Xcel Energy Notice of Project
June 20, 2025 20256-220093-10 Xcel Energy Appendix G - Phase 1 Archaeological Reconnaissance Survey Report
June 20, 2025 20256-220093-06 Xcel Energy Appendix C - Agency, Public, and Tribal Outreach and Correspondence
June 20, 2025 20256-220093-05 Xcel Energy Appendix B - Application Completeness Checklist
June 20, 2025 20256-220093-02 Xcel Energy Application for Site Permit
June 20, 2025 20256-220093-04 Xcel Energy Appendix A - Notice of Intent to File Site Permit Application
June 20, 2025 20256-220093-13 Xcel Energy Appendix J - Threatened & Endangered Species Documents
June 20, 2025 20256-220093-09 Xcel Energy Appendix F - Sound Study
June 20, 2025 20256-220093-08 Xcel Energy Appendix E - Preliminary Decommissioning Plan
June 20, 2025 20256-220093-11 Xcel Energy Appendix H - Greenhouse Gas Analysis
June 20, 2025 20256-220093-03 Xcel Energy Maps
June 20, 2025 20256-220093-01 Xcel Energy Cover Letter
June 20, 2025 20256-220093-12 Xcel Energy Appendix I - Wetland Delineation Report
June 20, 2025 20256-220093-07 Xcel Energy Appendix D - Preliminary Vegetation Management Plan
June 20, 2025 20256-220093-14 Xcel Energy Appendix K - Project Costs
May 22, 2025 20255-219189-01 Xcel Energy Notice of Intent for Alternative Review