Castle Rock Solar Project

Project Details

Docket Numbers
Project Name
Castle Rock Solar Project
Applicant
Castle Rock Solar, LLC
Location
Dakota County
Description

Castle Rock Solar, LLC is proposing to construct an up to 150-megawatt solar energy generating facility in Dakota County, Minnesota.
 

Status
active

Project Contact

Contact
Lauren Agnew
Phone

Project Summary

Castle Rock Solar, LLC (Castle Rock Solar), an independent power producer and wholly owned subsidiary of Midcontinental Renewables, LLC, seeks a permit to construct and operate an up to 150 megawatt (MW) alternating current photovoltaic solar energy generating facility and associated infrastructure in Dakota County, Minnesota. Castle Rock Solar proposes to develop the project on approximately 934 acres within a site of 1,355 acres in Castle Rock Township. Castle Rock Solar is currently engaged in easement negotiations for up to 60 additional acres for the routing of approximately 1,000 feet (up to two acres) of collection lines to connect two PV array areas in the southwest corner of the site. The additional 60 acres may also potentially host solar arrays depending on final landowner lease agreements.

Castle Rock Solar has designed this project with two potential connection scenarios: the Preferred Option and the Alternate Option. The Preferred Option and the Alternate Option layouts are largely the same with some minor deviations based on the configuration of the Project substation and other facilities. Both the Preferred and Alternate Option layouts will interconnect to the grid via a 138 kilovolt (kV) gen-tie line that connects to Xcel Energy’s existing Chub Lake to Hampton Corners 345kV transmission line that runs along 230th Street West and bisects the site. The Preferred Option would utilize an approximately 200-foot-long gen-tie line while the Alternate Option would utilize an approximately 1,450- foot-long gen-tie line.

Interactive Map

Key Project Documents

Date Title Description
July 17, 2025 Castle Rock Solar Scoping Decision ENVIRONMENTAL ASSESSMENT SCOPING DECISION
January 25, 2025 Castle Rock Solar Project Site Permit Application The site permit application for the Castle Rock Solar Project in Dakota County, Minnesota.

Docket Documents

View All Project Documents 

Date Title On Behalf Of Description
August 19, 2025 20258-222221-01 Castle Rock Solar, LLC Acquisition Occurrence Notice
July 21, 2025 20257-221245-01 OAH First Prehearing Order
July 11, 2025 20257-220883-01 PUC EIP Notice of Environmental Assessment Scoping Decision
July 9, 2025 20257-220799-01 PUC Notice of Legislative Changes
July 9, 2025 20257-220804-01 PUC EIP ENVIRONMENTAL ASSESSMENT SCOPING DECISION
June 16, 2025 20256-219941-01 Castle Rock Solar, LLC Duehr and Pai
June 12, 2025 20256-219854-01 Castle Rock Solar, LLC Castle Rock - Notice of Appearance - Duehr and Pai
June 10, 2025 20256-219771-01 OAH Order for Continued Prehearing Conference
May 6, 2025 20255-218653-01 DOC EERA Written Comments on the Scope of Environmental Assessment
May 6, 2025 20255-218652-01 DOC EERA Oral Comments on the Scope of Environmental Assessment
May 2, 2025 20255-218560-01 Minnesota Department of Natural Resources
May 2, 2025 20255-218560-02 Minnesota Department of Natural Resources Natural Heritage Review Letter
May 2, 2025 20255-218574-01 PUC Drea Doffing
April 29, 2025 20254-218290-01 OAH Order for Prehearing Conference
April 28, 2025 20254-218207-01 PUC Scoping Meeting Presentation
April 22, 2025 20254-218004-01 Castle Rock Solar LLC Update on Project Area Description
April 15, 2025 20254-217651-01 PUC Sample Site Permit
March 26, 2025 20253-216827-01 PUC NOTICE OF PUBLIC INFORMATION AND ENVIRONMENTAL ASSESSMENT SCOPING MEETINGS
March 19, 2025 20253-216627-01 PUC Authorization to Initiate Consultation under Minn. Stat. § 138.665
March 18, 2025 20253-216516-01 PUC
March 17, 2025 20253-216445-01 PUC Consent Items
March 13, 2025 20253-216366-01 PUC Proposed Consent Items
February 26, 2025 20252-215802-01 DOC EERA
February 26, 2025 20252-215808-01 LIUNA Minnesota/North Dakota
February 21, 2025 20252-215671-02 Castle Rock Solar LLC Attachment B to Reply Comments -NHIS Spreadsheet - PUBLIC
February 21, 2025 20252-215671-01 Castle Rock Solar LLC Completeness Reply Comments
February 14, 2025 20252-215393-01 DOC EERA ON APPLICATION COMPLETENESS
February 14, 2025 20252-215420-01 IUOE Local 49 and NCSRC of Carpenters
February 12, 2025 20252-215304-01 Castle Rock Solar LLC 2025-02-12 Castle Rock - Project Notice Compliance Filing
February 11, 2025 20252-215233-01 PUC