Beaver Creek Transmission Line Project
Project Details
Dairyland Power Cooperative (Dairyland) is proposing to construct an approximately 3.5 mile 161 kilovolt (kV) high voltage transmission line and associated facilities on a new right-of-way in York Township in Fillmore County, Minnesota.
Project Contact
Project Summary
The proposed Beaver Creek Transmission Line project starts at the intersection of the existing 161 kV LQ8A Harmony to Beaver Creek transmission line and 171st Avenue in York Township in Fillmore County, Minnesota and travels south approximately 3.5 miles and crosses the Minnesota-Iowa border at the southern border of York Township. From the border, it will continue westerly and southerly through Howard County, Iowa and terminate at a new proposed 161 kV switchyard to be constructed in Howard County, Iowa.
Interactive Map
Key Project Documents
Date | Title | Description |
---|---|---|
04/11/2025 | Beaver Creek Environmental Assessment | Environmental Assessment for Beaver Creek |
Docket Documents
View Project Documents (last 30) View All Project Documents
Date | Document ID | On Behalf Of | Description |
---|---|---|---|
September 22, 2025 | 20259-223203-01 | PUC | |
September 22, 2025 | 20259-223194-01 | PUC | ORDER ADOPTING ADMINISTRATIVE LAW JUDGE REPORT, DETERMINING ENVIRONMENTAL ASSESSMENT ADEQUATE, AND ISSUING SITE PERMIT |
September 10, 2025 | 20259-222859-01 | PUC | Northwestern Farm Management Company |
September 10, 2025 | 20259-222884-01 | PUC | September 11, 2025 Agenda, New/Revised Decisin Options-Commissiner Partridge |
September 8, 2025 | 20259-222789-01 | PUC | Draft Permit |
August 29, 2025 | 20258-222472-01 | PUC | September 11, 2025 |
August 26, 2025 | 20258-222432-01 | PUC | September 11, 2025 Agenda |
August 13, 2025 | 20258-222016-01 | PUC | August 14, 2025 Agenda, Final Revised Staff Briefing Papers |
August 12, 2025 | 20258-221993-01 | PUC | August 14, 2025, Revised Staff Briefing Papers - FILED IN ERROR |
August 12, 2025 | 20258-221978-01 | Dairyland Power Cooperative | Letter |
August 11, 2025 | 20258-221954-01 | PUC | PUC EIP Staff Exceptions to ALJ Report |
August 11, 2025 | 20258-221969-01 | PUC | August 14, 2025 Agenda, New Decision Option & Motion-Commissioner Tuma |
August 8, 2025 | 20258-221912-01 | PUC | August 14, 2025 Agenda - Revised |
August 7, 2025 | 20258-221880-02 | PUC | August 14, 2025 Agenda, Proposed Permit |
August 7, 2025 | 20258-221880-01 | PUC | August 14, 2025 Agenda |
August 1, 2025 | 20258-221683-01 | Snowshoe BESS, LLC | 2025-08-01 Snowshoe BESS Exceptions to ALJ Report |
August 1, 2025 | 20257-221548-01 | PUC | August 14, 2025 Agenda Meeting |
July 28, 2025 | 20257-221499-01 | OAH | Findings of Fact, Conclusions of Law and Recommendations |
July 23, 2025 | 20257-221320-01 | PUC EIP | EIP Staff Exceptions to ALJ Report |
July 9, 2025 | 20257-220799-01 | PUC | Notice of Legislative Changes |
July 9, 2025 | 20257-220774-01 | OAH | Findings of Fact, Conclusions of Law, and Recommendation |
July 9, 2025 | 20257-220799-01 | PUC | Notice of Legislative Changes |
June 9, 2025 | 20256-219707-01 | DOC EERA | |
June 6, 2025 | 20256-219661-01 | DOC - EERA | EERA Reply Comments and Response to Applicant's Proposed Findings of Facts |
May 27, 2025 | 20255-219265-02 | Dairyland Power Cooperative | Beaver Creek - Proposed Findings of Fact Conclusions of Law and Recommendations |
May 27, 2025 | 20255-219264-01 | Dairyland Power Cooperative | Beaver Creek - Response to Comments |
May 27, 2025 | 20255-219265-01 | Dairyland Power Cooperative | Beaver Creek - Findings of Fact Filing Letter |
May 23, 2025 | 20255-219232-01 | Snowshoe BESS, LLC | 2025-05-23 Snowshoe BESS_Response to Public Hearing Comments |
May 23, 2025 | 20255-219234-02 | Snowshoe BESS, LLC | Snowshoe BESS_ LLC Proposed FOF_ Conclusions of Law |
May 23, 2025 | 20255-219234-03 | Snowshoe BESS, LLC | Snowshoe Final Master Exhibit List |