Benton Solar Project

Project Details

Docket Numbers
Project Name
Benton Solar Project
Applicant
Benton Solar, LLC
Location
Benton County
Description

Benton Solar, LLC proposes to construct a 100 megawatt (MW) solar energy generating facility, a 100 MW battery energy storage system, and a 0.4 mile long, 115 kilovolt high voltage transmission line within Minden Township, Benton County, Minnesota.

Status
active

Project Contact

Contact
Logan Hicks
Phone

Project Summary

Benton Solar, LLC, a wholly owned, indirect subsidiary of NextEra Energy Resources, is requesting a site permit for the Benton County Solar Project, a 100 megawatt (MW) alternating current nameplate capacity solar energy conversion facility paired with a 100 MW battery energy storage system and associated facilities to be located in Minden Township, Benton County, Minnesota. The project will also include a 115 kilovolt, 0.4 mile long transmission line to deliver energy from the project to the electric grid.

Interactive Map

Key Project Documents

Date Title Description
August 4, 2025 Notice of Public Hearings Notice of Public Hearings
July 24, 2025 Benton Solar Environmental Assessment Benton Solar Environmental Assessment
March 27, 2025 Environmental Assessment Scoping Decision The Environmental Assessment Scoping Decision for the Benton Solar Project
September 26, 2024 Route Permit Application The route permit application for the Benton Solar Project transmission line in Benton County, Minnesota.
September 26, 2024 Joint Site Permit Application The joint site permit application for the Benton Solar Project solar facility and battery energy storage in Benton County, Minnesota.

Docket Documents

View All Project Documents 

Date Title On Behalf Of Description
August 19, 2025 20258-222234-01 Benton Solar, LLC Cover Letter, Affidavits of Publication, Certificate of Service
August 15, 2025 20258-222174-04 LIUNA Minnesota and North Dakota
August 15, 2025 20258-222174-05 LIUNA Minnesota and North Dakota
August 15, 2025 20258-222174-01 LIUNA Minnesota and North Dakota
August 15, 2025 20258-222158-01 Benton Solar, LLC Filing letter and certificate of service
August 15, 2025 20258-222174-02 LIUNA Minnesota and North Dakota
August 15, 2025 20258-222174-06 LIUNA Minnesota and North Dakota
August 15, 2025 20258-222158-02 Benton Solar, LLC Surrebuttal Testimony of Adam Gracia
August 15, 2025 20258-222174-03 LIUNA Minnesota and North Dakota
August 12, 2025 20258-221968-01 OAH Second Prehearing Order
August 6, 2025 20258-221840-02 Benton Solar, LLC Rebuttal Testimony of Adam Gracia with Schedule 1
August 6, 2025 20258-221843-03 LIUNA Minnesota and North Dakota Benton Solar Cortina Direct Testimony
August 6, 2025 20258-221843-01 LIUNA Minnesota and North Dakota Benton Solar Franco Direct Testimony
August 6, 2025 20258-221840-01 Benton Solar, LLC Benton Solar's Transmittal Letter
August 6, 2025 20258-221843-02 LIUNA Minnesota and North Dakota Benton Solar Analysis - Franco Direct Testimony Attachment A
August 6, 2025 20258-221844-02 LIUNA Minnesota and North Dakota Benton Solar Franco Rebuttal Testimony
August 6, 2025 20258-221840-03 Benton Solar, LLC Certificate of Service Re Rebuttal Testimony of Adam Gracia with Schedule 1
August 6, 2025 20258-221843-04 LIUNA Minnesota and North Dakota Corrected Testimony Cover Letter
August 6, 2025 20258-221844-01 LIUNA Minnesota and North Dakota Benton Solar LIUNA Rebuttal Testimony Cover
August 5, 2025 20258-221782-01 PUC EIP Notification of EA Mailed to Public Library
August 4, 2025 20258-221704-01 PUC NOTICE OF PUBLIC HEARINGS AND AVAILABILITY OF ENVIRONMENTAL ASSESSMENT
July 25, 2025 20257-221387-01 PUC EIP Notice of EA Availability to State Agencies and Tribal Historic Preservation Officers
July 24, 2025 20257-221364-01 PUC EIP Benton Solar Environmental Assessment
July 18, 2025 20257-221186-03 LIUNA Minnesota/North Dakota Benton Solar Cortina Direct Testimony
July 18, 2025 20257-221186-01 LIUNA Minnesota/North Dakota Benton Solar Franco Testimony
July 18, 2025 20257-221186-02 LIUNA Minnesota/North Dakota Franco Testimony
July 9, 2025 20257-220799-01 PUC Notice of Legislative Changes
June 30, 2025 20256-220514-02 Benton Solar, LLC Direct Testimony of Adam Gracia (With Schedule 1)
June 30, 2025 20256-220514-05 Benton Solar, LLC Direct Testimony of Ashley Nunez (With Schedule 1)
June 30, 2025 20256-220514-01 Benton Solar, LLC Benton Solar, LLC's Filing Submittal Correspondence