Birch Coulee Solar Project

Project Details

Docket Numbers
Project Name
Birch Coulee Solar Project
Applicant
Birch Coulee Solar, LLC
Location
Renville County
Description

Birch Coulee Solar, LLC is proposing to construct an up to 125-megawatt photovoltaic solar energy generating facility in Renville County, Minnesota.

Status
active

Project Contact

Contact
Lauren Agnew
Phone

Project Summary

Birch Coulee Solar, LLC (Birch Coulee Solar), an affiliate of AES Clean Energy (AES), seeks a permit to construct and operate an up to 125-megawatt (MW) alternating current photovoltaic solar energy generating facility and associated infrastructure in Renville County, Minnesota. Birch Coulee Solar proposes to develop the project on approximately 768.2 acres within a site of 1,041.6 acres in Birch Cooley, Camp, and Bandon Townships and the city of Franklin. As part of the project, Birch Coulee Solar proposes to construct a new project substation and an short (<500 feet) 115 kilovolt (kV) generation tie line to connect the new substation to the transmission owner's facilities.Birch Coulee Solar will file a site permit application for the project with the Public Utilities Commission in 2024, in Commission Docket No. IP7119/GS-23/477.

Interactive Map

Key Project Documents

Date Title Description
02/26/2025 Birch Coulee Solar Environmental Assessment Environmental Assessment for Birch Coulee Solar
11/26/2024 Birch Coulee Solar Project Environmental Assessment Scoping Decision Scoping decision on the environmental assessment to be prepared for the Birch Coulee Solar project.
11/26/2024 Birch Coulee Solar Project Prehearing Order The prehearing order for Birch Coulee Solar project includes the anticipated schedule of the process and protocol for public hearings.
09/13/2024 Birch Coulee Solar Project Site Permit Application The site permit application for the Birch Coulee Solar Project in Renville County, Minnesota.

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
September 9, 2025 20259-222816-01 Birch Coulee Solar, LLC Birch Coulee Solar - Site Permit Section 4.1 Site Permit Distribution Compliance Filing
August 11, 2025 20258-221950-01 PUC
July 30, 2025 20257-221556-01 PUC July 31, 2025 Agenda, New/Revised Decision Options 5m, 5n, 5g, 5k-Commissioner Tuma
July 30, 2025 20257-221552-01 PUC July 10, 2025 Agenda
July 28, 2025 20257-221494-01 Birch Coulee Solar LLC Decision Options
July 25, 2025 20257-221435-01 PUC July 31, 2025 Agenda, New/Revised Decision Options - Commissioner Tuma
July 24, 2025 20257-221360-01 PUC July 31, 2025 Agenda
July 18, 2025 20257-221021-01 PUC July 31, 2025 Agenda Meeting
July 10, 2025 20257-220828-01 PUC
July 9, 2025 20257-220799-01 PUC Notice of Legislative Changes
July 8, 2025 20257-220750-01 PUC Prohibited Ex Parte Communication Report
July 8, 2025 20257-220757-01 PUC July 10, 2025 Agenda, New/Revised Decision Option-Commissioner Tuma
July 7, 2025 20257-220650-01 PUC Ann Brazil
July 7, 2025 20257-220650-02 PUC Xcel Response to Ann Brazil
July 3, 2025 20257-220684-02 PUC Xcel Response to Ann Brazil
July 3, 2025 20257-220631-01 PUC July 10, 2025 Agenda - Updated
July 2, 2025 20257-220592-01 PUC July 10, 2025 Agenda
June 27, 2025 20256-220238-01 PUC July 10, 2025 Agenda Meeting
June 20, 2025 20257-220684-01 PUC Ann Brazil
May 30, 2025 20255-219402-01 DOC EERA EERA Exceptions to ALJ
May 29, 2025 20255-219373-01 Birch Coulee Solar LLC
May 15, 2025 20255-218971-01 OAH Findings of Fact, Conclusions of Law and Recommendation
April 14, 2025 20254-217622-03 DOC EERA Attachment B - EERA Edits to Proposed Findings of Facts
April 14, 2025 20254-217622-02 DOC EERA Attachment A - Amended Draft Site Permit
April 14, 2025 20254-217622-01 DOC EERA EERA Response
April 7, 2025 20254-217331-01 Birch Coulee Solar LLC Responses to Hearing Comments
April 7, 2025 20254-217329-02 Birch Coulee Solar LLC Proposed Findings of Fact, Conclusions of Law, and Recommendations
April 7, 2025 20254-217329-01 Birch Coulee Solar LLC Proposed Finding Filing Letter
March 24, 2025 20253-216743-02 Birch Coulee Solar LLC Comments on Environmental Assessment and Draft Site Permit
March 24, 2025 20253-216742-01 DOC EERA Hearing Comments