Laketown 115 kV Transmission Line Project

Project Details

Docket Numbers
Project Name
Laketown 115 kV Transmission Line Project
Applicant
Great River Energy
Location
Carver County
Description

Great River Energy proposes to construct a new 4.3 mile long 115 kV transmission line in Laketown and Dahlgren Townships in Carver County.

Status
active

Project Contact

Contact
Logan Hicks
Phone

Project Summary

Great River Energy (GRE) proposes to build a new 4.3 mile, 115 kilovolt (kV), double-circuit high voltage transmission line (HVTL) between an existing 115 kV transmission line and a new Laketown Township substation. The new proposed HVTL will begin at an existing GRE-owned 115 kV HVTL, and terminate at a proposed substation located within Laketown Township, owned by Minnesota Valley Electric Cooperative (MVEC).

The project is being proposed by GRE to provide electrical energy to the proposed new substation owned by MVEC which services customers in Carver, Sibley, Scott, Rice and LeSeuer counties.

Interactive Map

Key Project Documents

Date Title Description
04/08/2025 Laketown 115 kV Transmission Line Project Environmental Assessment Human and environmental impacts and mitigations for the proposed project
02/07/2025 Environmental Assessment Scoping Decision Environmental Assessment Scoping Decision
08/19/2024 Route Permit Application Great River Energy has submitted an application to the Public Utilities Commission for a Route Permit for the proposed Laketown 115 kV Transmission Line Project

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
October 2, 2025 202510-223519-01 PUC ORDER ADOPTING ADMINISTRATIVE LAW JUDGE REPORT AS MODIFIED, REQUIRING ADDITIONAL RECORD DEVELOPMENT, AND REMANDING FOR FURTHER PROCEEDINGS
September 10, 2025 20259-222877-01 PUC
September 2, 2025 20259-222652-02 Great River Energy and Minnesota Valley Electric Cooperative Laketown - Reply Comments re New and Modified Decision Options
September 2, 2025 20259-222652-01 Great River Energy and Minnesota Valley Electric Cooperative 2025-09-02 GRE - Laketown - Letter with Reply Comments to New and Modified Decision Options
September 2, 2025 20259-222652-03 Great River Energy and Minnesota Valley Electric Cooperative Laketown Reply Comments Attachment 1
August 27, 2025 20258-222462-01 PUC September 4, 2025 AGENDA - MODIFIED AND NEW DECISIONS OPTIONS - COMMISSIONER TUMA.
August 26, 2025 20258-222435-01 PUC EIP EIP Comments on Laketown Briefing Papers
August 25, 2025 20258-222377-01 PUC September 4, 2025
August 19, 2025 20258-222213-01 PUC September 4, 2025 Agenda
August 14, 2025 20258-222054-01 PUC EIP Laketown Map of Municipal Boundaries
July 31, 2025 20257-221612-01 PUC EIP Exceptions to ALJ Report
July 30, 2025 20257-221553-01 Great River Energy and Minnesota Valley Electric Cooperative GRE Laketown Exceptions to ALJ Report
July 17, 2025 20257-221078-01 OAH Findings of Fact, Conclusions of Law, and Recommendations
July 9, 2025 20257-220799-01 PUC Notice of Legislative Changes
June 17, 2025 20256-219944-01 DOC EERA Response to Proposed Findings
June 9, 2025 20256-219727-02 Great River Energy and Minnesota Valley Electric Cooperative Laketown - Filing Letter Proposed Findings
June 9, 2025 20256-219727-01 Great River Energy and Minnesota Valley Electric Cooperative Laketown Post Hearing Comments
June 9, 2025 20256-219727-03 Great River Energy and Minnesota Valley Electric Cooperative Laketown Proposed Findings of Fact, Conclusions of Law and Recommendations
June 4, 2025 20256-219581-01 PUC Tim and Patty Eiden
June 2, 2025 20256-219479-01 Minnesota Interagency Vegetation Management Planning Working Group Hearing Comments
June 2, 2025 20256-219508-02 MN Department of Natural Resources DNR Comment Letter Attachment
June 2, 2025 20256-219554-01 PUC City of Carver Mayor Courtney Johnson
June 2, 2025 20256-219508-01 MN Department of Natural Resources DNR Comment Letter
June 2, 2025 20256-219470-01 DOC EERA Public Hearing Comments
June 2, 2025 20256-219555-01 PUC Managers of Pierson Lake, LLC on behalf of members
May 30, 2025 20256-219463-01 PUC PC Pierson Lake
May 27, 2025 20255-219254-01 PUC Meeting Presentation
May 22, 2025 20255-219194-02 PUC City of Carver
May 22, 2025 20255-219194-01 PUC City of Victoria
May 22, 2025 20257-221504-03 Shaddix & Associates - Stenographic Court Reporters Virtual Public Hearing on 5-22-25