Laketown 115 kV Transmission Line Project

Project Details

Docket Numbers
Project Name
Laketown 115 kV Transmission Line Project
Applicant
Great River Energy
Location
Carver County
Description

Great River Energy proposes to construct a new 4.3 mile long 115 kV transmission line in Laketown and Dahlgren Townships in Carver County.

Status
active

Project Contact

Contact
Logan Hicks
Phone

Project Summary

Great River Energy (GRE) proposes to build a new 4.3 mile, 115 kilovolt (kV), double-circuit high voltage transmission line (HVTL) between an existing 115 kV transmission line and a new Laketown Township substation. The new proposed HVTL will begin at an existing GRE-owned 115 kV HVTL, and terminate at a proposed substation located within Laketown Township, owned by Minnesota Valley Electric Cooperative (MVEC).

The project is being proposed by GRE to provide electrical energy to the proposed new substation owned by MVEC which services customers in Carver, Sibley, Scott, Rice and LeSeuer counties.

Interactive Map

Key Project Documents

Date Title Description
04/08/2025 Laketown 115 kV Transmission Line Project Environmental Assessment Human and environmental impacts and mitigations for the proposed project
02/07/2025 Environmental Assessment Scoping Decision Environmental Assessment Scoping Decision
08/19/2024 Route Permit Application Great River Energy has submitted an application to the Public Utilities Commission for a Route Permit for the proposed Laketown 115 kV Transmission Line Project

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
February 17, 2026 20262-228243-01 PUC February 26, 2026 Agenda Meeting
February 13, 2026 20262-228178-01 PUC February 26, 2026 Agenda
February 5, 2026 20262-227888-01 Great River Energy and Minnesota Valley Electric Cooperative Supplemental Findings
February 3, 2026 20262-227797-01 PUC EIP Exceptions to Supplemental ALJ Report
January 28, 2026 20261-227517-01 CAH Supplemental Findings of Fact, Conclusions of Law, and Recommendation
January 7, 2026 20261-226600-01 PUC EIP Response to Proposed Supplemental Findings
January 7, 2026 20261-226594-01 PUC Outside of Comment Period - Jack Worm
December 30, 2025 202512-226345-01 PUC Received outside comment period - Patty Eiden
December 30, 2025 202512-226319-01 Great River Energy Laketown Letter with Supplemental Proposed Findings of Fact, Conclusions of Law, and Recommendations
December 23, 2025 202512-226177-01 Great River Energy Laketown - Letter with Reply Comments
December 23, 2025 202512-226136-01 Minnesota Valley Electric Cooperative
December 18, 2025 202512-225996-01 PUC Don Schlegelmilch
December 17, 2025 202512-225936-01 PUC Russell Schlegelmilch
December 17, 2025 202512-225949-01 PUC Anthony Schuster
December 17, 2025 202512-225940-01 PUC Jo Eiden
December 17, 2025 202512-225951-01 PUC City of Carver
December 17, 2025 202512-225950-01 PUC Patty Eiden
December 17, 2025 202512-225952-01 PUC Greg Boe
December 16, 2025 202512-225923-01 PUC Batch 1 12162025 - 9 Comments
December 16, 2025 202512-225903-01 Great River Energy and Minnesota Valley Electric Cooperative Initial Comments
December 15, 2025 202512-225858-01 Xcel Energy COMMENTS - GREAT RIVER ENERGY'S ROUTE PERMIT APPLICATION FOR THE LAKETOWN
December 12, 2025 202512-225823-01 PUC
December 5, 2025 202512-225603-01 PUC City of Victoria
November 17, 2025 202511-224978-01 PUC NOTICE OF COMMENT PERIOD ON INDEPENDENT CONSULTANT REPORT AND FOR ADDITIONAL RECORD DEVELOPMENT
November 7, 2025 202511-224791-01 POWER Engineers Independent reliability and cost review of GRE Proposed and Alternative B routes.
October 29, 2025 202510-224454-01 PUC September 4, 2025 Minutes
October 28, 2025 202510-224338-01 PUC EIP Laketown Environmental Assessment Appendix C Supplement
October 28, 2025 202510-224363-01 PUC EIP Notification of EA Appendix C Supplement Mailed to Public Library
October 22, 2025 202510-224203-01 CAH Third Prehearing Order
October 22, 2025 202511-224632-01 Shaddix & Associates - Stenographic Court Reporters Prehearing held on 10-22-25