Iron Pine Solar Project
Project Details
Iron Pine Solar Power, LLC is proposing an up to 325-megawatt photovoltaic solar energy generating system and a 230-kilovolt high voltage transmission line in Kettle River Township, Pine County, Minnesota.
Project Contact
Project Summary
Iron Pine Solar Power, LLC (Iron Pine Solar), a wholly owned subsidiary of Swift Current Energy, seeks permits to construct and operate an up to 325 megawatt (MW) alternative current photovoltaic solar energy generating facility (project) in Pine County, Minnesota. Iron Pine Solar proposes to develop the project on approximately 1,537 acres within a site of 2,207 acres in Kettle River Township. As part of the project, Iron Pine Solar proposes to construct a new project substation and an approximate one mile 230 kilovolt (kV) generation tie line to connect the generating facility to a new switchyard to be constructed by Iron Pine Solar to connect the new transmission line to the existing Minnesota Power Arrowhead-Bear Creek 230 kV transmission line. Iron Pine Solar filed a joint application for a site permit and route permit for the project with the Public Utilities Commission on May 15, 2023, in Commission Docket Nos. IP7114/GS-23-414 and TL-23-415.
Interactive Map
Key Project Documents
Date | Title | Description |
---|---|---|
January 8, 2025 | Iron Pine Solar Environmental Assessment | The environmental assessment prepared for the proposed Iron Pine Solar project. The assessment discusses the potential human and environmental impacts of the project and possible mitigation measures. |
September 5, 2024 | Iron Pine Solar Project Scoping Decision | The Department of Commerce issued the scoping decision for the Iron Pine Solar Project. |
May 16, 2024 | Iron Pine Solar Joint Site and Route Permit Application | Iron Pine Solar Joint Site and Route Permit Application |
Docket Documents
View Project Documents (last 30) View All Project Documents
Date | Title | On Behalf Of | Description |
---|---|---|---|
August 11, 2025 | 20258-221949-01 | PUC | Erratum |
August 6, 2025 | 20258-221830-01 | PUC | COMPLIANCE LETTER |
August 5, 2025 | 20258-221783-01 | PUC | PUC EIP Compliance Review |
August 4, 2025 | 20258-221713-01 | PUC | Consent |
August 4, 2025 | 20258-221729-01 | PUC | |
August 1, 2025 | 20258-221671-01 | PUC | Proposed Consent Item |
July 31, 2025 | 20257-221590-01 | PUC EIP | on Permit Amendment Request |
July 31, 2025 | 20257-221615-01 | Iron Pine Solar Power, LLC | Iron Pine Solar - Reply Comments on Amendment Request |
July 23, 2025 | 20257-221321-01 | Iron Pine Solar Power, LLC | Pre-Construction Filing |
July 22, 2025 | 20257-221266-01 | PUC | NOTICE OF COMMENT PERIOD ON PERMIT AMENDMENT REQUEST |
July 18, 2025 | 20257-221166-01 | Iron Pine Solar Power, LLC | Request for Amendment of Permit Conditions |
July 16, 2025 | 20257-221033-01 | PUC | June 5, 2025 Agenda |
July 15, 2025 | 20257-220989-01 | PUC | |
July 9, 2025 | 20257-220799-01 | PUC | Notice of Legislative Changes |
June 30, 2025 | 20256-220426-01 | PUC | Kelly Applegate |
June 30, 2025 | 20256-220469-01 | PUC | Mille Lacs Band of Ojibwe Reply - Charlie Lippert |
June 30, 2025 | 20256-220507-01 | PUC | Tuma Decision Options |
June 24, 2025 | 20256-220160-01 | PUC | JULY 1, 2025 AGENDA |
June 24, 2025 | 20256-220168-01 | PUC | JULY 1, 2025 AGENDA - Revised briefing papers |
June 24, 2025 | 20256-220160-03 | PUC | JULY 1, 2025 AGENDA - Iron Pine Site Permit All Attachments |
June 24, 2025 | 20256-220168-02 | PUC | JULY 1, 2025 AGENDA - Revised Site Permit |
June 24, 2025 | 20256-220160-02 | PUC | JULY 1, 2025 AGENDA-Iron Pine Route Permit All Attachments |
June 20, 2025 | 20256-220005-01 | PUC | July 1, 2025 Agenda Meeting |
May 27, 2025 | 20255-219259-01 | PUC | JUNE 5, 2025 AGENDA |
May 23, 2025 | 20255-219214-01 | PUC | JUNE 5, 2025 AGENDA |
May 12, 2025 | 20255-218777-01 | Iron Pine Solar Power, LLC | |
May 12, 2025 | 20255-218850-01 | DOC EERA | |
April 25, 2025 | 20254-218138-01 | OAH | Findings of Fact, Conclusions of Law and Recommendation |
March 27, 2025 | 20253-216936-01 | DOC EERA | |
March 12, 2025 | 20253-216337-01 | Iron Pine Solar Power, LLC | Response to Public Hearing Comments |