Xcel Energy's Sherco 3 Solar Project

Project Details

Docket Numbers
Project Name
Xcel Energy's Sherco 3 Solar Project
Applicant
Xcel Energy
Location
Sherburne County
Description

Xcel Energy proposes to construct a new 250 MW solar energy project in Sherburne County, Minnesota

Status
active

Project Contact

Contact
Suzanne Steinhauer
Phone

Project Summary

Xcel Energy proposes to construct a new 250 MW solar energy project in Sherburne County, Minnesota

Interactive Map

Key Project Documents

Date Title Description
August 27, 2024 Site Permit for Sherco Solar 3 Project The Commission issued a site permit for the Sherco Solar 3 Project on July 31, 2024.
April 22, 2024 Sherco Solar 3 Environmental Assessment The Environmental Assessment (EA) prepared by the Minnesota Department of Commerce for the Sherco Solar 3 Project in Sherburne County. The EA analyzes the potential impacts of the project and possible mitigation measures.
August 11, 2023 Xcel Energy Application for a Site Permit for the Sherco 3 Solar Project. On August 8, 2023, Xcel Energy submitted a site permit application to the Minnesota Public Utilities Commission under the alternative review process (Minnesota Statute 216E.04; Minnesota Rule 7850.2800-3900) for the Sherco 3 Solar Project

Docket Documents

View All Project Documents 

Date Title On Behalf Of Description
August 15, 2025 20258-222167-01 Xcel Energy Xcel Sherco 3 - July Monthly Progress Report Compliance Filing
August 15, 2025 20258-222167-04 Xcel Energy Xcel Sherco 3 - July Complaint Report -PUBLIC
August 15, 2025 20258-222167-02 Xcel Energy Xcel Sherco 3 - Q2 Quarterly Wildlife Injuries Report Compliance Filing
August 15, 2025 20258-222167-03 Xcel Energy Xcel Sherco 3 - Q2 Quarterly Labor Statistics Report Compliance Filing
August 13, 2025 20258-222043-01 PUC EIP Environmental Review Compliance Review - Revised Site Clearing Plans
August 1, 2025 20258-221670-01 Xcel Energy Xcel Sherco 3 - Site Plan Update
July 15, 2025 20257-220975-01 Xcel Energy Sherco 3_ June 2025 Progress Report
July 15, 2025 20257-220975-02 Xcel Energy Sherco 3 - June 2025 Complaint Report
June 13, 2025 20256-219879-02 Xcel Energy 2025-06-13 Xcel - Sherco 3 - Complaint Report - May 25 - PUBLIC
June 13, 2025 20256-219879-01 Xcel Energy 2025-06-13 Xcel Sherco 3_ Progress Report Compliance Filing - May 25
May 15, 2025 20255-218990-04 Xcel Energy Sherco Solar 3 - 1st Qtr 2025 Wildlife Injuries and Fatalities Filing
May 15, 2025 20255-218990-05 Xcel Energy Sherco Solar 3 - 1st Qtr 2025 Labor Statistics Report
May 15, 2025 20255-218990-01 Xcel Energy Sherco 3 - April 2025 Complaint Report
May 15, 2025 20255-218990-03 Xcel Energy Sherco 3_ April 2025 Progress Report
April 15, 2025 20254-217714-01 Xcel Energy Sherco 3_ March 2025 Progress Report Filing
April 15, 2025 20254-217714-02 Xcel Energy Sherco 3 - March 2025 Complaint Report
April 11, 2025 20254-217525-01 Xcel Energy 2025-04-11 Xcel Sherco 3 VSP Complaint Response
April 1, 2025 20254-217106-01 Xcel Energy Sherco 3 - Updated VSP filing
March 14, 2025 20253-216431-02 Xcel Energy February 2025 Complaint Report
March 14, 2025 20253-216431-01 Xcel Energy February 2025 Progress Report
February 14, 2025 20252-215423-05 Xcel Energy Solar 3 - 4th Quarter Wildlife Injuries and Fatalities
February 14, 2025 20252-215423-03 Xcel Energy Solar 3 - January 2025 Progress Report
February 14, 2025 20252-215423-02 Xcel Energy Solar 3 - January 2025 Complaint Report
February 14, 2025 20252-215423-04 Xcel Energy Solar 3 - 4th Quarter Labor Statistics Report
January 31, 2025 20251-214762-01 DOC EERA Complaint - Thomas Hentges
January 22, 2025 20251-214244-01 PUC to Xcel Energy
January 15, 2025 20251-214037-01 Xcel Energy December 2024 Status Report
January 15, 2025 20251-214038-01 Xcel Energy December 2024 Complaint Report
January 14, 2025 20251-213937-01 DOC - EERA EERA Compliance Review - Revised Site Clearing Plans
January 9, 2025 20251-213771-02 Xcel Energy 2025-01-09 Sherco 3 Site Plan Update