Minnesota Power HVDC Modernization Project

Project Details

Docket Numbers
Project Name
Minnesota Power HVDC Modernization Project
Applicant
Minnesota Power
Location
St. Louis County
Description

To modernize the Minnesota terminal of the existing Square Butte high voltage direct current (HVDC) line that runs from North Dakota to Northeast Minnesota, a new terminal, new substation, and three high voltage transmission lines are proposed on a new site near the existing Arrowhead Substation in St. Louis County, Minnesota.

Status
active

Project Contact

Contact
Jenna Ness
Phone

Project Summary

To modernize the Minnesota terminal of the existing Square Butte high voltage direct current (HVDC) line and implement the latest technology, new buildings and electrical infrastructure are proposed on a new site near the existing Arrowhead Substation in St. Louis County, MN. The new HVDC terminal is proposed to connect to the existing alternating current system by constructing a new St. Louis County 345 kilovolt (kV)/230 kV substation near the current Arrowhead Substation. The new HVDC terminal would be connected to the St. Louis County Substation by less than one mile of 345 kV high voltage transmission line (HVTL). The new St. Louis County Substation would be connected to the existing Arrowhead Substation by two parallel 230 kV HVTLs less than one mile in length. Additionally, a short portion of the existing ±250 kV HVDC line  will need to be reconfigured to terminate at the new HVDC terminal.

Updates and expansions are required at the other end of the Square Butte line in North Dakota as well, to be regulated by the North Dakota Public Service Commission. The project includes cupgrading to bi-directional transmission while maintaining the same voltage and power transfer capability along the Square Butte HVDC line. 

Interactive Map

Key Project Documents

Date Title Description
02/29/2024 Environmental Assessment The final environmental assessment for the Minnesota Power HVDC Modernization project has been released.
06/05/2023 Site Permit and Certificate of Need Application Initial filing for a Certificate of Need and a Route Permit to the Minnesota Public Utilities Commission.
10/29/2024 PUC Decision on Route Permit This order issuing a route permit for the project was made by the Public Utilities Commission on August 1, 2024.
10/29/2024 Route Permit This file contains the route permit and conditions for the HVDC Modernization Project.

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
September 12, 2025 20259-222949-01 Minnesota Power August 2025 Monthly Construction Status Report and Complaint Report
August 5, 2025 20258-221789-01 Minnesota Power July 2025 Monthly Construction Status Report and Complaint Report
July 16, 2025 20257-221051-01 Minnesota Power June 2025 Monthly Construction Status Report and Complaint Report
June 4, 2025 20256-219578-01 Minnesota Power May 2025 Construction Status Report and Complaint Report
May 19, 2025 20255-219066-01 Minnesota Power MN HVDC Modern - April 2025 Construction Compliance Filing
April 11, 2025 20254-217542-01 Minnesota Power March 2025 Construction Compliance Filing
April 4, 2025 20254-217262-01 DOC
February 28, 2025 20252-215901-01 PUC Preconstruction Compliance Filing
February 20, 2025 20252-215625-01 PUC January 7, 2025 Minutes
February 19, 2025 20252-215544-01 DOC EERA
February 13, 2025 20252-215374-01 Minnesota Power Summary of Project's Pre-Construction Meeting
February 11, 2025 20252-215260-01 Minnesota Power Project Field Representative Contact Information and Affidavit of Mailing
January 29, 2025 20251-214580-01 Minnesota Power HVDC Converter Station Noise Study and Affidavit of D. McCourtney re Permit Approvals
January 27, 2025 20251-214452-01 Minnesota Power 2025 01 27 MN HVDC Converter Station Grading Plan
January 9, 2025 20251-213750-01 PUC Denying Petition for Reconsideration
December 31, 2024 202412-213439-01 PUC January 7, 2025 agenda
December 26, 2024 202412-213315-01 PUC January 7, 2025 Agenda
December 17, 2024 202412-213128-01 Minnesota Power Notice of Withdrawal
December 10, 2024 202412-212876-01 Minnesota Power Avian Coordination
December 4, 2024 202412-212678-01 Minnesota Power 2024 12 04 HVDC Modern Pre Const Permit and 3rd Party Monitor Compliance Filing
November 25, 2024 202411-212395-02 Minnesota Power Answer to LPI's Petition for Reconsideration
November 25, 2024 202411-212395-01 Minnesota Power Answer Filing Letter
November 22, 2024 202411-212303-01 PUC August 1, 2024 Minutes
November 14, 2024 202411-211959-02 LARGE POWER INTERVENORS LPI FILING LETTER, CERTIFICATE OF SERVICE, AND SERVICE LISTS
November 14, 2024 202411-211959-04 LARGE POWER INTERVENORS LPI PETITION FOR RECONSIDERATION
November 11, 2024 202411-211775-02 MINNESOTA POWER COMPLAINT HANDLING PROCEDURES AND PROJECTS VEGETATION MANAGEMENT PLAN
November 1, 2024 202411-211524-02 MINNESOTA POWER NOTICE OF WITHDRAWAL-PETER MADSEN
October 25, 2024 202410-211332-02 PUC ORDER GRANTING CERTIFICATE OF NEED AND ISSUING ROUTE PERMIT
August 1, 2024 20248-209181-02 DEPARTMENT OF NATURAL RESOURCES
July 31, 2024 20247-209128-01 PUC AUGUST 1, 2024 AGENDA-NEW DECISION OPTION 8 - COMMISSIONER TUMA