Pine Bend Pipeline Project
Project Details
Petroleum Fuels Company (PFC) is proposing to construct a 5,600 foot long natural gas pipeline in Dakota County. The pipeline will transport natural gas from a processing facility near the Pine Bend landfill to an interconnection with the Northern States Power gas system.
Project Contact
Project Summary
Petroleum Fuels Company (PFC) is proposing to construct a 5,600 foot long natural gas pipeline in Dakota County. The pipeline will transport natural gas from a processing facility near the Pine Bend landfill to an interconnection with the Northern States Power gas system.
The pipeline will be 4.5 inches in diameter and will operate at a presssure of approximately 670 pounds per square inch (psi). The project will require a 30 foot easement.
PFC has applied to the Minnesota Public Utilities Commission for a pipeline routing permit for the project. PFC received a pipeline routing permit from the Commission on July 7, 2021.
Map Image
Key Project Documents
Date | Title | Description |
---|---|---|
July 7, 2021 | Route Permit for the Pine Bend Pipeline Project | The Commission's route permit issued for the Pine Bend pipeline project. |
July 7, 2021 | Commission Order Issuing Route Permit | The Commission order issuing a route permit for the Pine Bend pipeline project. Includes order, findings of fact, and a route permit. |
December 30, 2020 | Route Permit Application for the Pine Bend Pipeline Project | The route permit application for the Pine Bend pipeline project submitted by Petroleum Fuels Company (PFC) to the Minnesota Public Utilities Commission. |
Docket Documents
View Project Documents (last 30) View All Project Documents
Date | Title | On Behalf Of | Description |
---|---|---|---|
May 19, 2022 | 20225-185899-01 | PETROLEUM FUELS COMPANY | 10.3 FILING FOR NOTICE OF OPERATIONS |
February 9, 2022 | 20222-182584-02 | PUC | FEBRUARY 18, 2021 AGENDA |
November 8, 2021 | 202112-180710-01 | PETROLEUM FUELS COMPANY | 10.5_GPS DATA |
November 1, 2021 | 202112-180690-01 | PETROLEUM FUELS COMPANY | COMPLIANCE FILING - 10.4 - AS-BUILTS |
October 28, 2021 | 202110-179266-01 | PETROLEUM FUELS COMPANY | ROUTE PERMIT SECTIONS 10.2 AND 10.3 |
October 14, 2021 | 202110-178809-01 | PETROLEUM FUELS COMPANY | STATUS REPORT |
September 30, 2021 | 20219-178396-01 | PETROLEUM FUELS COMPANY | ROUTE PERMIT SECTION 10.2 - STATUS REPORT |
September 16, 2021 | 20219-178020-01 | PETROLEUM FUELS COMPANY | STATUS REPORT 10.2 SEPTEMBER 1ST - 15TH, 2021 |
September 3, 2021 | 20219-177697-01 | PUC | |
August 30, 2021 | 20218-177578-01 | DOC EERA | |
August 17, 2021 | 20218-177226-01 | PETROLEUM FUELS COMPANY | ROUTE PERMIT SECTIONS 4.1 - 4.4 |
August 16, 2021 | 20218-177295-01 | PETROLEUM FUELS COMPANY | MNPUC HEARING REQUEST - GREENHOUSE GAS OFFSET |
August 16, 2021 | 20218-177381-01 | PETROLEUM FUELS COMPANY | ROUTE PERMIT SECTION 5.5.10 |
August 16, 2021 | 20218-177289-01 | PETROLEUM FUELS COMPANY | ROUTE PERMIT SECTIONS 5.5.8 |
August 16, 2021 | 20218-177293-01 | PETROLEUM FUELS COMPANY | ROUTE PERMIT FINDINGS OF FACT 53 |
August 16, 2021 | 20218-177296-01 | PETROLEUM FUELS COMPANY | MNPUC HEARING REQUEST - LANDFILL CAPACITY |
August 16, 2021 | 20218-177415-01 | PETROLEUM FUELS COMPANY | ROUTE PERMIT SECTIONS 10.1 |
August 16, 2021 | 20218-177288-01 | PETROLEUM FUELS COMPANY | ROUTE PERMIT SECTIONS 4.6 |
August 16, 2021 | 20218-177291-01 | PETROLEUM FUELS COMPANY | ROUTE PERMIT SECTIONS 5.5.14 |
August 16, 2021 | 20218-177294-01 | PETROLEUM FUELS COMPANY | ROUTE PERMIT FINDINGS OF FACT 54 |
August 16, 2021 | 20218-177290-01 | PETROLEUM FUELS COMPANY | ROUTE PERMIT SECTIONS 5.5.13 |
August 16, 2021 | 20218-177380-01 | PETROLEUM FUELS COMPANY | COMPLIANCE FILING - SECTION 6.1 |
August 16, 2021 | 20218-177288-02 | PETROLEUM FUELS COMPANY | ROUTE PERMIT SECTIONS 5.1 - 5.4 |
August 16, 2021 | 20218-177292-01 | PETROLEUM FUELS COMPANY | ROUTE PERMIT - CONTAMINATION SURVEY |
August 11, 2021 | 20218-177019-04 | PUC | JUNE 10, 2021 MINUTES |
July 16, 2021 | 20217-176237-01 | PETROLEUM FUELS COMPANY | COMPLAINT PROCEDURES CONTACT UPDATE |
July 7, 2021 | 20217-175899-01 | PUC | ORDER GRANTING PARTIAL EXEMPTION TO PIPELINE ROUTE PERMIT PROCEDURES AND ISSUING ROUTE PERMIT |
June 9, 2021 | 20216-174909-01 | PUC | JUNE 10, 2021 AGENDA - REVISED DECISION OPTIONS-COMMISSIONER TUMA |
June 8, 2021 | 20216-174890-01 | PETROLEUM FUELS COMPANY | SUPPLEMENT TO PROPOSED FINDINGS OF FACT, CONCLUSIONS OF LAW AND RECOMMENDATIONS |
June 2, 2021 | 20216-174768-01 | PUC | JUNE 10, 2021 AGENDA |