Plum Creek Wind Farm and Associated 345 kV Transmission Line Project
Project Details
Plum Creek Wind Farm, LLC proposes to construct a 414 megawatt (MW) wind farm and associated 345 kV transmission line in Cottonwood, Murray, and Redwood County, Minnesota.
Project Contact
Project Summary
Plum Creek Wind Farm, LLC (Plum Creek or Applicant), a subsidiary of Geronimo Power, LLC, proposes to construct a 414 MW wind farm in Cottonwood, Murray, and Redwood County. The wind farm would include up to 74 wind turbines; the final number of turbines will depend on the turbine type(s) selected for the project. Electric power from the turbines would be collected at two collector substations. The wind farm would be connected to the electric transmission grid by approximately 31 miles of 345 kilovolt (kV) transmission line. The line would interconnect with the existing Brookings County to Hampton 345 kV transmission line via a switching station in Redwood County.
On September 23, 2021, the Commission issued an order approving a certificate of need, site permit, and route permit to Plum Creek for the Plum Creek Project. In response to requests from Plum Creek, the Commission amended the site permits in January 2022 to clarify certain reporting requirements, in July 2023 to extend the time by which construction on the project must commence, and in September 2025 to use different turbine models, shift the location of a collector station, and extend the in-service date and date by which construction must commence.
Key Project Documents
Date
|
Title
|
Description
|
|---|---|---|
9/3/2025
|
Order Issuing Amended Site and Route Permit
|
|
2/4/2025
|
Site Permit Amendment Request
|
|
Route Permit Amendment Request
2/4/2025
|
Route Permit Amendment Request
|
Docket Documents
View Project Documents (last 30) View All Project Documents
| Date | Document ID | On Behalf Of | Description |
|---|---|---|---|
| March 3, 2026 | 20263-228875-01 | Plum Creek Wind Farm, LLC | 2026-03-03 Plum Creek Wind_SP Section 10.4 Status Report |
| September 3, 2025 | 20259-222666-01 | PUC | |
| July 30, 2025 | 20257-221552-01 | PUC | July 10, 2025 Agenda |
| July 10, 2025 | 20257-220824-01 | PUC | July 10, 2025 Agenda - Staff New Revised Decision Option 1 |
| July 9, 2025 | 20257-220799-01 | PUC | Notice of Legislative Changes |
| July 8, 2025 | 20257-220754-01 | Plum Creek Wind Farm, LLC | Update Regarding Status of Project |
| July 8, 2025 | 20257-220707-01 | PUC | Tuma Decision Options |
| July 7, 2025 | 20257-220705-01 | DOC | |
| July 7, 2025 | 20257-220705-02 | DOC | |
| July 3, 2025 | 20257-220637-01 | PUC | July 10, 2025 Agenda |
| July 1, 2025 | 20257-220576-01 | Plum Creek Wind Farm | Change in Ownership |
| June 27, 2025 | 20256-220238-01 | PUC | July 10, 2025 Agenda Meeting |
| June 24, 2025 | 20256-220183-01 | PUC | Jeremy Duehr & Marta Lasch |
| June 12, 2025 | 20256-219845-01 | PUC | Proposed Consent Items |
| April 8, 2025 | 20254-217355-01 | PUC | Consent, Revised |
| April 4, 2025 | 20254-217303-01 | PUC | Consent |
| April 3, 2025 | 20254-217199-01 | PUC | Proposed Consent Items |
| March 21, 2025 | 20253-216692-01 | Plum Creek Wind Farm, LLC | Supplemental |
| March 17, 2025 | 20253-216461-01 | DOC - EERA | EERA Supplemental Comments on Permit Amendment Requests |
| March 12, 2025 | 20253-216336-01 | Plum Creek Wind Farm, LLC | 2025-03-12 Plum Creek - Reply Comments re request to amend permits |
| March 12, 2025 | 20253-216345-01 | MN Department of Natural Resources | DNR Comment Letter |
| March 12, 2025 | 20253-216345-02 | MN Department of Natural Resources | DNR Comment Letter - Attachment |
| March 6, 2025 | 20253-216128-01 | PUC | Dennis Fultz |
| March 5, 2025 | 20253-216089-01 | DOC EERA | EERA Comments and Recommendations on Permit Amendment Requests |
| March 4, 2025 | 20253-216039-01 | PUC | Robert and Jeanette Heggerston |
| February 24, 2025 | 20252-215702-01 | PUC | Jean Knakmuhs |
| February 24, 2025 | 20252-215702-02 | PUC | Jean Knakmuhs |
| February 24, 2025 | 20252-215702-03 | PUC | Jean Knakmuhs |
| February 12, 2025 | 20252-215297-01 | PUC | on Extension/Variance |
| February 4, 2025 | 20252-214951-03 | Plum Creek Wind Farm, LLC | Appendix A_Draft Site Permit Amendment |