Revised Site Permit Application
The revised project would still be located in Vienna Township of Rock County. The primary
components of the facility would include photovoltaic panels affixed to a linear axis tracking rack system, inverters, step-up transformers, electrical cables and conduits, electrical cabinets, access roads, a 34.5/161- kilovolt (kV) step-up substation with metering and switching gear, security fencing, below-ground or above-ground electrical collection and communication lines, an operation and maintenance facility, parking lot, up to two weather stations, a 161 kV overhead transmission line (under 1,500 feet in length), a supervisory control and data acquisition system, and temporary laydown areas. The project would interconnect to the existing 161 kV Magnolia Substation adjacent to the project site.
Site Permit Application
Figure 2 2023 Land Control and Preliminary Development Areas
Figure 3 Preliminary Project Layout
Figures 4a Detailed Preliminary Project Layout
Figures 4b Detailed Preliminary Project Layout
Figures 4c Detailed Preliminary Project Layout
Figures 4d Detailed Preliminary Project Layout
Figures 4e Detailed Preliminary Project Layout
Figures 4f Detailed Preliminary Project Layout
Figures 4g Detailed Preliminary Project Layout
Figures 4h Detailed Preliminary Project Layout
Figures 4i Detailed Preliminary Project Layout
Figures 4j Detailed Preliminary Project Layout
Figures 4k Detailed Preliminary Project Layout
Figure 5 Potential Solar Development Constraints
Figure 6 Regional Prime Farmland
Figure 9 Existing Infrastructure and AADT
Figure 10 Farmland Classifications
Appendix A Agency Correspondence
Appendix C Agricultural Impact Mitigation Plan and Vegetation Management Plan (part 1)
Appendix C Agricultural Impact Mitigation Plan and Vegetation Management Plan (part 2)