Northland Reliability 345 kV Transmission Line Project

Project Details

Docket Numbers
Project Name
Northland Reliability 345 kV Transmission Line Project
Applicant
Minnesota Power and Great River Energy
Location
Description

Minnesota Power and Great River Energy propose to construct approximately 140 miles of new double-circuit 345 kV transmission line and to replace approximately 40 miles of existing transmission line with double-circuit 345 kV transmission line. The project would connect the existing Iron Range substation, near Grand Rapids, Minn., to a new Big Oaks substation near Monticello, Minn.

Status
active

Project Contact

Contact
Jim Sullivan
Phone

Project Summary

Minnesota Power and Great River Energy (applicants) propose to construct approximately 140 miles of new double-circuit 345 kV transmission line and to replace approximately 40 miles of existing transmission line with double-circuit 345 kV transmission line. The project would connect the existing Iron Range substation, near Grand Rapids, Minn., to a new Big Oaks substation near Monticello, Minn.

The project requires a certificate of need (CN) and route permit from the Minnesota Public Utilities Commission (Commission). A CN and a route permit must be issued by the Commission before construction of the project may begin. Department of Commerce, Energy Environmental Review and Analysis (EERA) staff will prepare an environmental assessment for the project on behalf of the Commission. Public meetings and public hearings will be held for the project.  

The applicants anticipate obtaining a CN and route permit from the Commission in 2024, with project construction beginning in 2025.

Interactive Map

Key Project Documents

Date Title Description
February 28, 2025 Order granting Certificate of Need and Issu In the Matter of the Application of Minnesota Power and Great River Energy for a Certificate of Need and Route Permit for an Approximately 180-mile, Double Circuit 345-kV Transmission Line
November 8, 2024 Administrative Law Judge Report -- Findings of Fact, Conclusions of Law, and Recommendation The final report of the Administrative Law Judge. It includes written comments, filings, and testimony provided at public hearings. The report also provides recommendations regarding the project. The Minnesota Public Utilities Commission will use the report in making certificate of need and route permit decisions.
July 1, 2024 Environmental Assessment Documents - Northland Reliability Project Environmental Assessment document that includes appendices and maps.
August 4, 2023 Combined Certificate of Need and Route Permit Application The combined certificate of need and route permit application for the proposed Northland Reliability Project

Docket Documents

View All Project Documents 

Date Title On Behalf Of Description
August 11, 2025 20258-221958-01 Minnesota Power and Great River Energy Updated Plan and Profile Filing for Segment 2
July 25, 2025 20257-221420-01 Minnesota Power and Great River Energy Affidavit of Mailing for Vegetation Management Plan
July 22, 2025 20257-221272-01 Great River Energy and Minnesota Power NRP Irrigation Compliance Filing
July 21, 2025 20257-221236-08 Minnesota Power and Great River Energy Plan and Profile for Segment 2 - Attachment C
July 21, 2025 20257-221236-06 Minnesota Power and Great River Energy Plan and Profile for Segment 2 - Attachment A-3
July 21, 2025 20257-221236-07 Minnesota Power and Great River Energy Plan and Profile for Segment 2 - Attachment B
July 21, 2025 20257-221236-03 Minnesota Power and Great River Energy Plan and Profile for Segment 2 - Attachment A-1.2
July 21, 2025 20257-221236-01 Minnesota Power and Great River Energy Plan and Profile for Segment 2 - Cover Letter
July 21, 2025 20257-221236-02 Minnesota Power and Great River Energy Plan and Profile for Segment 2 - Attachment A-1.1
July 21, 2025 20257-221236-04 Minnesota Power and Great River Energy Plan and Profile for Segment 2 - Attachment A-2.1
July 21, 2025 20257-221236-05 Minnesota Power and Great River Energy Plan and Profile for Segment 2 - Attachment A-2.2
July 21, 2025 20257-221236-09 Minnesota Power and Great River Energy Plan and Profile for Segment 2 - Attachment D
July 16, 2025 20257-221035-01 PUC EIP Irrigators Association of Minnesota Comment, July 16, 2025
July 16, 2025 20257-221035-01 PUC EIP Irrigators Association of Minnesota Comment, July 16, 2025
July 15, 2025 20257-221065-01 PUC Irrigators Association MN
July 15, 2025 20257-221065-01 PUC Irrigators Association MN
July 11, 2025 20257-220888-01 Minnesota Power and Great River Energy Monthly Construction Status Report and Complaint Report for June 2025
July 7, 2025 20257-220703-01 Minnesota Power and Great River Energy Vegetation Management Plan
June 27, 2025 20256-220449-01 PUC Sherburne Cty Board of Commissioners_Outside Comment Period
June 27, 2025 20256-220449-01 PUC Sherburne Cty Board of Commissioners_Outside Comment Period
June 26, 2025 20256-220327-01 PUC Concerning pre-construction compliance documents filed by Great River Energy and Minnesota Power on May 21, 2025, and June 13, 2025, in connection with the Northland Reliability Project in Aitkin, Benton, Crow Wing, Itasca, Morrison, and Sherburne counties.
June 26, 2025 20256-220327-01 PUC Concerning pre-construction compliance documents filed by Great River Energy and Minnesota Power on May 21, 2025, and June 13, 2025, in connection with the Northland Reliability Project in Aitkin, Benton, Crow Wing, Itasca, Morrison, and Sherburne counties.
June 18, 2025 20256-219999-01 DOC EERA EERA Compliance Review Letter and Comments June 18, 2025
June 18, 2025 20256-219999-01 DOC EERA EERA Compliance Review Letter and Comments June 18, 2025
June 13, 2025 20256-219890-01 Minnesota Power and Great River Energy Pre-Construction Meeting and Third-Party Monitor Compliance Filing
May 21, 2025 20255-219161-01 Great River Energy and Minnesota Power 2025-05-21 GRE_NRP_Benton Substation_Construction_RP 6.7 Compliance Filing
May 13, 2025 20255-218907-01 PUC Jean Johnson
May 13, 2025 20255-218907-01 PUC Jean Johnson
May 2, 2025 20255-218654-01 PUC Received Outside Comment Period- Nancy and Jerry Doucette
May 2, 2025 20255-218654-01 PUC Received Outside Comment Period- Nancy and Jerry Doucette