Big Stone South to Alexandria 345 kV Transmission Line Project

Project Details

Docket Numbers
Project Name
Big Stone South to Alexandria 345 kV Transmission Line Project
Applicant
Otter Tail Power Company and Western Minnesota Municipal Power Agency, through its agent, Missouri River Energy Services (collectively, the Applicants)
Location
Douglas County, Pope County, Stevens County, Swift County, Big Stone County
Description

The Applicants propose to construct over 90 miles of new transmission line from Big Stone South, South Dakota to Alexandria, Minnesota along portions of Big Stone, Swift, Stevens, Pope, and Douglas Counties. New transmission lines will be required to connect the existing substations in Big Stone South and Alexandria. Both of the existing substations would also require minor expansions. A new fiber optic Regeneration Station would also be needed within the central segment of the project on 0.23 acres of land.
 

Status
active

Project Contact

Contact
Jenna Ness
Phone

Project Summary

The Applicants propose to construct over 90 miles of new transmission line from Big Stone South, South Dakota to Alexandria, Minnesota along portions of Big Stone, Swift, Stevens, Pope, and Douglas Counties. The project is needed to provide additional transmission capacity, mitigate current capacity issues, and improve electric system reliability.

The Big Stone South to Alexandria project is the West segment of the larger Big Stone South – Alexandria – Big Oaks 345 kV transmission line project which has obtained a certificate of need (CN-22-538) as a whole. This project comprises the West segment from Big Stone South to Alexandria which filed for a separate route permit application than the East Alexandria to Big Oaks segment, which has already recieved a route permit.

Interactive Map

Key Project Documents

Date Title Description
09/26/2025 Notice of Information Meetings NOTICE OF INFORMATION MEETINGS, PUBLIC AND EVIDENTIARY HEARINGS, AND AVAILABILITY OF DRAFT ENVIRONMENTAL IMPACT STATEMENT
09/04/2025 Draft Environmental Impact Statement: Main Text Draft Environmental Impact Statement: Main Text for the Big Stone South to Alexandria 345 kV Transmission Line Project
09/04/2025 EIS Maps 01-10 Environmental Impact Statement for the Big Stone South to Alexandria 345 kV Transmission Line Project, Maps 01-10
09/04/2025 EIS Maps 11-17 Environmental Impact Statement for the Big Stone South to Alexandria 345 kV Transmission Line Project, Maps 11-17
09/04/2025 EIS Maps 18-20 Environmental Impact Statement for the Big Stone South to Alexandria 345 kV Transmission Line Project, Maps 18-20
09/04/2025 EIS Appendices A-E Environmental Impact Statement for the Big Stone South to Alexandria 345 kV Transmission Line Project, Appendices A to E
09/04/2025 EIS Appendix F F-01 to F-15 Environmental Impact Statement for the Big Stone South to Alexandria 345 kV Transmission Line Project, Appendix F (F-01 to F-15)
09/04/2025 EIS Appendix F F-16 to F-29 Environmental Impact Statement for the Big Stone South to Alexandria 345 kV Transmission Line Project, Appendix F (F-16 to F-29)
09/04/2025 EIS Appendix F F-30 to F-50 Environmental Impact Statement for the Big Stone South to Alexandria 345 kV Transmission Line Project, Appendix F (F-30 to F-50)
09/04/2025 EIS Appendix F F-51 to F-65 Environmental Impact Statement for the Big Stone South to Alexandria 345 kV Transmission Line Project, Appendix F (F-51 to F-65)
09/04/2025 EIS Appendices G-N Environmental Impact Statement for the Big Stone South to Alexandria 345 kV Transmission Line Project, Appendices G-N
05/06/2025 Environmental Impact Statement Scoping Decision Document The Scoping Decision Document outlines what topics will be covered in the Environmental Impact Statement for the project.
02/27/2025 Project Schedule Attached is the prehearing order issued by the Administrative Law Judge assigned to the Big Stone South to Alexandria 345 kV Transmission project. This document contains the milestones associated with the project's schedule in the route permitting and environmental review process.
10/22/2024 Route Permit Application On October 22, 2024, the applicants filed a route permit application for the Big Stone South to Alexandria 345-kV Transmission Project with the Minnesota Public Utilities Commission.
09/29/2023 Certificate of Need Application On September 29, 2023, the applicants filed a certificate of need application for the entire project (Big Stone South to Alexandria to Big Oaks) with the Minnesota Public Utilities Commission.

Docket Documents

View All Project Documents 

Date Document ID On Behalf Of Description
October 3, 2025 202510-223595-01 CAH Order Canceling Evidentiary Hearing
October 1, 2025 202510-223463-01 PUC Leslie Meek
October 1, 2025 202510-223464-01 PUC Grant Minnerath
October 1, 2025 202510-223466-01 CAH Order for Prehearing Conference
September 30, 2025 20259-223402-01 PUC Bill and Marilyn Anderson
September 29, 2025 20259-223381-01 PUC Meeting Presentation
September 26, 2025 20259-223347-01 Troy Schmidtke
September 26, 2025 20259-223348-01 Otter Tail Power Company and Western Minnesota Municipal Power Agency Filing Letter
September 26, 2025 20259-223348-02 Otter Tail Power Company and Western Minnesota Municipal Power Agency DEIS Comments
September 26, 2025 20259-223403-01 PUC The Swensons
September 24, 2025 20259-223262-01 PUC Aaron & Michelle Knutson
September 24, 2025 20259-223262-02 PUC Brent Walker
September 23, 2025 20259-223235-01 Otter Tail Power Company and Western Minnesota Municipal Power Agency Errata to Direct Testimony
September 22, 2025 20259-223224-01 PUC MPCA
September 15, 2025 20259-222977-02 Otter Tail Power Company and Western Minnesota Municipal Power Agency Weiers Rebuttal Testimony
September 15, 2025 20259-222977-01 Otter Tail Power Company and Western Minnesota Municipal Power Agency Filing Letter, COS, and Service List
September 11, 2025 20259-223287-01 PUC EIP Certificate of Mailing Draft EIS to Libraries
September 4, 2025 20259-222715-02 PUC EIP Draft Environmental Impact Statement Appendix F: (F-16 through F-29)
September 4, 2025 20259-222710-08 PUC EIP Draft Environmental Impact Statement Appendix F (F-51 through F-65)
September 4, 2025 20259-222710-01 PUC EIP Draft Environmental Impact Statement: Main Text
September 4, 2025 20259-222710-06 PUC EIP Draft Environmental Impact Statement: Appendices G-N
September 4, 2025 20259-222715-01 PUC EIP Draft Environmental Impact Statement Appendix F: (F-1 through F-15)
September 4, 2025 20259-222710-02 PUC EIP Draft Environmental Impact Statement: Maps 1-10
September 4, 2025 20259-222710-07 PUC EIP Draft Environmental Impact Statement: Appendix F (F-30 through F-50)
September 4, 2025 20259-222710-04 PUC EIP Draft Environmental Impact Statement: Maps 18-20
September 4, 2025 20259-222690-01 PUC NOTICE OF INFORMATION MEETINGS, PUBLIC AND EVIDENTIARY HEARINGS, AND AVAILABILITY OF DRAFT ENVIRONMENTAL IMPACT STATEMENT
September 4, 2025 20259-222710-03 PUC EIP Draft Environmental Impact Statement: Maps 11-17
September 4, 2025 20259-222710-05 PUC EIP Draft Environmental Impact Statement: Appendices A-E
September 2, 2025 20259-222688-01 PUC EIP Notice of Hearings and draft EIS in EQB Monitor
August 15, 2025 20258-222128-03 Otter Tail Power Company and Western Minnesota Municipal Power Agency Weiers Direct Testimony and Schedules A-C Part 2 of 4